The issue is ProjectPeriod.
Try:
CF Gantt =
VAR StartDate =
CALCULATE ( MIN ( v_ProjectGantt[ProjectStartDate] ), REMOVEFILTERS ( 'Date' ) )
VAR EndDate =
CALCULATE ( MIN ( v_ProjectGantt[ProjectEndDate] ), REMOVEFILTERS ( 'Date' ) )
VAR ProjectPeriod =
FILTER (
VALUES ( 'Date'[Date] ),
MIN ( 'Date'[Date] ) >= StartDate
&& MIN ( 'Date'[Date] ) <= EndDate
)
VAR ProjectStatus =
CALCULATE ( MIN ( v_ProjectGantt[CompletionStatus] ), REMOVEFILTERS ( 'Date' ) )
VAR Result =
SWITCH (
TRUE (),
MAX ( Date[Date] )
IN ProjectPeriod
&& ProjectStatus = "Completed", 1,
MAX ( Date[Date] )
IN ProjectPeriod
&& ProjectStatus = "Delayed", 2,
MAX ( Date[Date] )
IN ProjectPeriod
&& ProjectStatus = "Open", 3
)
RETURN
Result
Proud to be a Super User!
Paul on Linkedin.
The issue is ProjectPeriod.
Try:
CF Gantt =
VAR StartDate =
CALCULATE ( MIN ( v_ProjectGantt[ProjectStartDate] ), REMOVEFILTERS ( 'Date' ) )
VAR EndDate =
CALCULATE ( MIN ( v_ProjectGantt[ProjectEndDate] ), REMOVEFILTERS ( 'Date' ) )
VAR ProjectPeriod =
FILTER (
VALUES ( 'Date'[Date] ),
MIN ( 'Date'[Date] ) >= StartDate
&& MIN ( 'Date'[Date] ) <= EndDate
)
VAR ProjectStatus =
CALCULATE ( MIN ( v_ProjectGantt[CompletionStatus] ), REMOVEFILTERS ( 'Date' ) )
VAR Result =
SWITCH (
TRUE (),
MAX ( Date[Date] )
IN ProjectPeriod
&& ProjectStatus = "Completed", 1,
MAX ( Date[Date] )
IN ProjectPeriod
&& ProjectStatus = "Delayed", 2,
MAX ( Date[Date] )
IN ProjectPeriod
&& ProjectStatus = "Open", 3
)
RETURN
Result