Gauge visualisation using %
Hi there I have some data displayed in a gauge. I want to show the values, maximum value and then the values also shown as a percentage. It doesn't seem possible to do this. Is it possible or ...
- 3 years ago
Hi automate2create ,
For this you can add the value has the target and then show the target value has the maximum value.:
MFelix
3 years agoSuper User
Hi automate2create ,
The maximum and minimum on the gauge chart are based on the values of the chart itself so if you are placing a % and then have a min of 5000 the values don't appear on the chart.
Why don't you aplly the values on the gauge has you have on the first but then turn off the callout value and place the card percentage on the midle you just need to set up the formatting of the card
Be aware that my values only go to 100 that's why the percentage is the sasame has the value