Forum Discussion
Gantt visualisation displaying multiple dependencies
- Anonymous4 years ago
Good news - xViz does have a solution for >2 dependencies. It's possible to just use the primary connector and configure the dependencies in a single column in PowerBI with the correct syntax and delimiter. See their post here
Thanks ronaldbalza2023 . See below for a sample of the Gantt Chart I've created using xViz.
As an example, the third task listed here has 3 dependencies. I'm able to use the "Primary Connector" and "Secondary Connector" in xViz to display 2 of the 3 dependencies, however I'm unable to display the 3rd dependency.
Am hoping there might be an alternative Gantt visualisation that is capable of achieving this outcome (or some way to configure same in xViz)?
Many thanks
Good news - xViz does have a solution for >2 dependencies. It's possible to just use the primary connector and configure the dependencies in a single column in PowerBI with the correct syntax and delimiter. See their post here