Hi,

 

I have a Gantt Chart all set up like a time line showing me hours in a day (duration unit set to minutes in general settings), using timestamp (date/time) as start and end.  Everything is working perfectly except I cannot add a duration.  When I try to add a data field to the duration in the visual menu nothing happens, it won't stick.

 

The duration is in minutes.  I've tried transforming it to a duration, tired a new calculated column (End-Start), tried converting that to minutes, hours, days.  Nothing seems to work!  Am I missing something?

1 ACCEPTED SOLUTION
Anonymous
Not applicable

@pedanticpad 

I cannot enter Endtime and Duration field at the same time, try only enter column in to duration only.


Paul Zheng _ Community Support Team
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

View solution in original post

6 REPLIES 6
Pragati11
Super User
Super User

Hi @pedanticpad ,

 

Please share some screenshots around what you are trying to do here.

It's hard to understand what you are trying to achieve using Gantt chart. Also, add some sample data so that we can try to replicate at our end.

 

Thanks,

Pragati

Best Regards,

Pragati Jain


MVP logo


LinkedIn | Twitter | Blog YouTube 

Did I answer your question? Mark my post as a solution! This will help others on the forum!

Appreciate your Kudos!!

Proud to be a Super User!!

Sorry.  I thought I made sense when I wrote that.  See screenshot below, absolutely no field will populate in the Duration field.  No matter what I drag and drop it will not enter this field.  I though it something to do with my duration measure but no field at all will go into the Duration field in the settings.  Has anyone come accross this before?

 

image.png

Anonymous
Not applicable

@pedanticpad 

I cannot enter Endtime and Duration field at the same time, try only enter column in to duration only.


Paul Zheng _ Community Support Team
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

Anonymous
Not applicable

Which Gantt Chart are you using?

@

 

Hi @pedanticpad ,

 

Refer following link to see what DURATION value is epected in this Gantt chart. It looks more like that you have to create a new column with CALENDAR duration.

https://www.senseiprojectsolutions.com/2018/03/23/creating-calendar-duration-for-use-with-the-gantt-...

 

Thanks,

Pragati

Best Regards,

Pragati Jain


MVP logo


LinkedIn | Twitter | Blog YouTube 

Did I answer your question? Mark my post as a solution! This will help others on the forum!

Appreciate your Kudos!!

Proud to be a Super User!!

Helpful resources

Announcements
Join our Fabric User Panel

Join our Fabric User Panel

Share feedback directly with Fabric product managers, participate in targeted research studies and influence the Fabric roadmap.

February Power BI Update Carousel

Power BI Monthly Update - February 2026

Check out the February 2026 Power BI update to learn about new features.

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.