Forum Discussion
Gantt automatically count %completion?
- Anonymous8 years ago
Hallo Lydia,
First of all i want too thank you for your helping hand.
The problem is of the relationship between the 2 tables wasn't working right.
I made a new table and used the command Append Queries. Now i was able to make te right relationship between the 2 tables.
Regards,
Charaf
thx for your reply,
It workt for the example but not for the real deal. I cant understand why. Sorry for my newbie questions.
Anonymous,
You would need to drag Druu.1 field to Duration of Gantt chart, please review the following screenshots.
Regards,
Lydia
- Anonymous8 years agoNot applicable
This is the result. I feel im close.This is the result but its not accurate
- Anonymous8 years agoNot applicable
Anonymous,
Why do you drag Staus field to %Completion of Gantt chart? In the third screenshot of your original post, you drag Completion field of Werkorders table to %Completion of Gantt chart.
Regards,
Lydia- Anonymous8 years agoNot applicable
1. Completion= the status field that are marked with verification.
2. The screenshot in the original qeustion was a simplified data table too see if it works.
3 the last screenshot are the orginal data table were i have to implement it in. (its more advanced)