Hallo everybody,
Is it possible to let the gantt visual completion count only the orders that are labelt with verification.
Maybe a other solution to automaticaly count the verification.
I simplified the tabels just to work out a concept
Duration = Verification + uitvoeren
Verification = %completion duration
it must be 2 different data tabels
- Anonymous8 years ago
Hallo Lydia,
First of all i want too thank you for your helping hand.
The problem is of the relationship between the 2 tables wasn't working right.
I made a new table and used the command Append Queries. Now i was able to make te right relationship between the 2 tables.
Regards,
Charaf
10 Replies
- AnonymousNot applicable
Anonymous,
Drag Status field to visual level filters of Gantt chart, and set its value to verificate, then check if you get expected result.
Regards,
Lydia- AnonymousNot applicable
thx for your reply,
It workt for the example but not for the real deal. I cant understand why. Sorry for my newbie questions.
- AnonymousNot applicable
Anonymous,
You would need to drag Druu.1 field to Duration of Gantt chart, please review the following screenshots.
Regards,