Gantt - Sub Tasks & Parent
- 8 years ago
If you structure the tabel as
Start Duration Parent Task Complete Resource
2018-01-01 0 AAA
2018-01-01 10 AAA A1 10% Name1
2018-01-15 20 AAA A2 30% Name2
2018-02-01 40 BBB 0% Name 3
You will get an arrow at the parent AAA.
Hi
It was working in 1.10 but then stopped working in 1.11 (for me anyway). They have just released 1.13 (not visible in the store yet) with new improvements. I hope it will start working again in that version.
/
Link for the lazy.
https://github.com/Microsoft/powerbi-visuals-gantt/commit/cec20e893202cc65f83254dfae08f2285c594973