Hi there   Can someone point me in the right direction to get Gantt chart to work with: Parent Sub Tasks   And if possible explanations for Sub Tasks -> 'Inherit parent legend', 'Parent durat...
  • LostInTheFlood's avatar
    LostInTheFlood
    8 years ago

    If you structure the tabel as 

     

    Start                Duration    Parent    Task      Complete     Resource

    2018-01-01     0                               AAA

    2018-01-01     10              AAA        A1         10%             Name1

    2018-01-15     20              AAA        A2          30%            Name2

    2018-02-01     40                            BBB         0%             Name 3

     

    You will get an arrow at the parent AAA.