If you structure the tabel as
Start Duration Parent Task Complete Resource
2018-01-01 0 AAA
2018-01-01 10 AAA A1 10% Name1
2018-01-15 20 AAA A2 30% Name2
2018-02-01 40 BBB 0% Name 3
You will get an arrow at the parent AAA.
Hi Aash_
Apologies, I haven't worked out yet how Anonymous's screenshot came about.
It may be to do with versions (a prior version had functionality and it's now no longer working. Maybe, I don't yet know).