Gantt - Sub Tasks & Parent
- 8 years ago
If you structure the tabel as
Start Duration Parent Task Complete Resource
2018-01-01 0 AAA
2018-01-01 10 AAA A1 10% Name1
2018-01-15 20 AAA A2 30% Name2
2018-02-01 40 BBB 0% Name 3
You will get an arrow at the parent AAA.
Appreciate it Anonymous.
The linked file doesn't have the dropdowns like your screenshot. Apologies if I'm missing something simple.
bretto Anonymous
I'm experiencing the same issue; the items appear but as separate 'tasks' and not as dropdowns of the parent. Would appreciate any solutions or workarounds.
- meflec8 years ago
Microsoft Employee
I am also having trouble with this. The subtasks do group by parent, and the parent task has a bolder color. However, no arrow to colapse the subtasks. I think this is a critical feature and should be added as an obvious Formating selection. Thanks!
- bretto8 years ago
Helper I
Hey - I've posted this as an idea. May get some attention if other people have this issue.