Gantt - Sub Tasks & Parent
Hi there Can someone point me in the right direction to get Gantt chart to work with: Parent Sub Tasks And if possible explanations for Sub Tasks -> 'Inherit parent legend', 'Parent durat...
- 8 years ago
If you structure the tabel as
Start Duration Parent Task Complete Resource
2018-01-01 0 AAA
2018-01-01 10 AAA A1 10% Name1
2018-01-15 20 AAA A2 30% Name2
2018-02-01 40 BBB 0% Name 3
You will get an arrow at the parent AAA.
BarryM
3 years agoHelper II
I am actually having an issue with the 'Parent', I have 8 items in that field but only 6 are displaying in the Gantt Chart.
From Gantt Chart
From Table of Parent Items