Forum Discussion
JTESE
7 years agoNew Member
Gantt Chart by MAQSoftware | Hierarchy Layout Rollup Calculation
I am having an issue with the roll-up totals when "Category > Hierarchy layout" is enabled and there is a Visual Level Filter or Page Filter applied. Unfiltered it rolls up correctly: ...
Quentin
Helper IV
7 years agoI am facing exactly the same issue...
Have you found some workaround or solutions?
Thank you for sharing!
Quentin
- JTESE7 years agoNew MemberUnfortunately not... Please reply though if your luckier than I have been!
- Quentin7 years ago
Helper IV
In my case it's even worse as my labels are persentage of completion, therefore i would like the upper category not to sum on it but to do the average:
result1
result1 Activity 1 progress 10%
result1 Activity 2 progress 20%
I would like progress of result1 to be 15%...
I sent a message to MAQSupport, let's see if they manage to help us- Anonymous5 years agoNot applicable
Hi Quentin,
Did you hear back from MAQSupport ? Did you resolve the issue ?
I have the same problem. In my case, the rollup is simply adding up the percentages rather then using the measure. The measure works fine in the matrix visual.