Gantt Chart (alternate schedules in one window)

Hi,

 

I'm using the basic Gantt chart visualiser. I want to add slicer/check box where I can alternate between two set of dates (baseline dates and current dates) on the same window.

 

Can this be done on Power BI and how?

 

Ahmed K.

1 ACCEPTED SOLUTION
Anonymous
Not applicable

Hi @ahmedKalbani,

 

One way of doing this is with buttons and bookmarks.

Create 2 different Gantt charts and 2 bookmarks for the same page, with each bookmark showing a different Gantt chart. Then assign buttons to theses bookmarks to create the effect that they filter the chart.

 

Here's a reference.

 

Br,

 

T

View solution in original post

2 REPLIES 2
Anonymous
Not applicable

Hi @ahmedKalbani,

 

One way of doing this is with buttons and bookmarks.

Create 2 different Gantt charts and 2 bookmarks for the same page, with each bookmark showing a different Gantt chart. Then assign buttons to theses bookmarks to create the effect that they filter the chart.

 

Here's a reference.

 

Br,

 

T

Thanks. that was the direction I needed.

Helpful resources

Announcements
Power BI DataViz World Championships

Power BI Dataviz World Championships

The Power BI Data Visualization World Championships is back! Get ahead of the game and start preparing now!

December 2025 Power BI Update Carousel

Power BI Monthly Update - December 2025

Check out the December 2025 Power BI Holiday Recap!

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.