Gantt Chart Half Days

Hello,

 

I am trying to create a gantt chart to display a construction schedule. We occasionally have tasks which take 12h, or half a day assuming 24h work.

 

My dataset recognizes that the task is only 12h. It starts at 7am and ends at 7pm, with the following task starting at 7pm and ending at 7am. So two tasks have been scheduled for one 24h block. See the "Calculated Scheduled Start/End Time" columns below. 

 

jmiller2224_0-1634163457180.png

 

 

On the Gantt chart, each of these 12h tasks are being displayed as 24h, but maintaining the correct start times. As a result, the durations are incorrect and there is overlap between subsequent tasks ("Mobilize" and "Rig up"). Does the graphing component just have a minimum duration of one day? Is there any known workarounds for this? I would like to display this schedule accurately. 

 

jmiller2224_1-1634163457208.png

 

jmiller2224_2-1634163457185.png

 

 

Any help would be greatly appreciated.

 

Thanks 

1 REPLY 1
bashheadonwall
New Member

This is very interesting to me. I wonder what @amitchandak or @Greg_Deckler 's view on this is.

Helpful resources

Announcements
Power BI DataViz World Championships

Power BI Dataviz World Championships

The Power BI Data Visualization World Championships is back! Get ahead of the game and start preparing now!

December 2025 Power BI Update Carousel

Power BI Monthly Update - December 2025

Check out the December 2025 Power BI Holiday Recap!

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.