Forum Discussion
Gantt 2.2.3 - % Completion
Hi Community,
I am currenlty working on Gantt 2.2.3. My data is as follows.
| Task | Start | Resource | Duration | % Completion |
| 1004-1211 | 25-10-2020 00:00 | 1464 | 15 | 0.95 |
I am not getting the progress line on visual. Please suggest where I am getting wrong. Please take a look at the attached sceenshot.
Gantt 2.2.3
- Anonymous5 years ago
Hi Anonymous ,
Did you mean that the black line shown below is missing in Gantt(2.3.3) ?
Please enable the Task Completion option.
Did I answer your question ? Please mark my reply as solution. Thank you very much.
If not, please upload some insensitive data samples and expected output.Best Regards,
Eyelyn Qin
3 Replies
- AnonymousNot applicable
Hi Anonymous ,
Did you mean that the black line shown below is missing in Gantt(2.3.3) ?
Please enable the Task Completion option.
Did I answer your question ? Please mark my reply as solution. Thank you very much.
If not, please upload some insensitive data samples and expected output.Best Regards,
Eyelyn Qin- AnonymousNot applicable
Anonymous Thank you very much!!
- bakerm00Regular Visitor
its not just a case of enabling completion - i have to change the Max completion to 1 to honour actual % values in the data tables