I am currenlty working on Gantt 2.2.3.  My data is as follows.

 

TaskStartResourceDuration% Completion
1004-121125-10-2020 00:001464150.95

 

I am not getting the progress line on visual.  Please suggest where I am getting wrong.  Please take a look at the attached sceenshot.

 

Gantt 2.2.3

 

 

  • Anonymous's avatar
    Anonymous
    5 years ago

    Hi Anonymous ,

    Did you mean that the black line shown below is missing in Gantt(2.3.3) ? 

    Please enable the Task Completion option. 

     

    Here is the pbix file.

     

    Did I answer your question ? Please mark my reply as solution. Thank you very much.
    If not, please upload some insensitive data samples and expected output.

     

    Best Regards,
    Eyelyn Qin

3 Replies

  • Anonymous's avatar
    Anonymous
    Not applicable

    Hi Anonymous ,

    Did you mean that the black line shown below is missing in Gantt(2.3.3) ? 

    Please enable the Task Completion option. 

     

    Here is the pbix file.

     

    Did I answer your question ? Please mark my reply as solution. Thank you very much.
    If not, please upload some insensitive data samples and expected output.

     

    Best Regards,
    Eyelyn Qin

    • Anonymous's avatar
      Anonymous
      Not applicable

      Anonymous Thank you very much!!

  • bakerm00's avatar
    bakerm00
    Regular Visitor

    its not just a case of enabling completion - i have to change the Max completion to 1 to honour actual % values in the data tables