Ive such a simple question but im unable to fix it.
I need to plan an activity base upon another activity and therefore i need to subtract 14 days from a date column but the result returns a date in the year 1899
The formula is simple
Hi, it will depend in where you solve this. You have to create a new column. If you want to solve it in edit queries check "AddDays" function. If you want to solve this with DAX check "DATEADD" function. In order to make it work the column has to be date type.
Hope this helps,
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
ibarrau ive corrected the problem and the right formula should be
Sisu gepland = dateadd(Adressen[civiel begin].[Date];-14;DAY)However do you know how to make sure it subtracts workingdays instead of just days because in this formula the date could be a saturday or sunday.I have a 'date' table with a column in it to check if its a weekday
4 Replies
- ibarrau
Super User
Hi, it will depend in where you solve this. You have to create a new column. If you want to solve it in edit queries check "AddDays" function. If you want to solve this with DAX check "DATEADD" function. In order to make it work the column has to be date type.
Hope this helps,
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
- RonaldvdH
Post Patron
ibarrau ive corrected the problem and the right formula should be
Sisu gepland = dateadd(Adressen[civiel begin].[Date];-14;DAY)However do you know how to make sure it subtracts workingdays instead of just days because in this formula the date could be a saturday or sunday.I have a 'date' table with a column in it to check if its a weekday- ibarrau
Super User
Power bi by default won't help you with working days. This is something you have to create, do some data modeling first.
Check this post talking about them: https://www.sqlbi.com/articles/counting-working-days-in-dax/
Right now your formula just substract days in general.
Regards,
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.