I have a Target Start Date (Date field) and a number in days for Preparation of a project (Num Field). I am trying to create a column that gives me a Start of Preparation Date. I can do this easily in excel but it is not working in PowerBi all i am getting is an error and other formula like DateAdd wants a fixed days and wont let me add a Number Field.
[Target Date]-[Preparation Days] = New column Start of Preparation Date
Thanks in advance 🙂
Solved! Go to Solution.
Hope this helps:
You can create a measure like this
If you want to create a calculated column, you can use ths following
Thank you so much for all the help!!!!!
Thank you so much, unfortunately i cant use NETWORKDAY on my version. I have to keep my version in order to share my reports on the system. The video it so good and explains everything so well
Hope this helps:
You can create a measure like this
If you want to create a calculated column, you can use ths following
Starting December 3, join live sessions with database experts and the Fabric product team to learn just how easy it is to get started.
March 31 - April 2, 2025, in Las Vegas, Nevada. Use code MSCUST for a $150 discount! Early Bird pricing ends December 9th.
User | Count |
---|---|
93 | |
90 | |
84 | |
70 | |
49 |
User | Count |
---|---|
141 | |
120 | |
112 | |
60 | |
58 |