Hi There ;

 

i need your kind help to create a measure , i tried to explain what i need ;

 

i have two table as below , one of them "purchasing"and the other one "inbound " , as you see i have "A "material 100 pcs which one is planned to delivery on 10.05.2020.But that goods not delivered on time ,  some of them early , some of them lately delivered , i need to calculate how many pcs of this order delivered on time or before according to planned date  .For below example i need to find "60" pcs because last 40 pcs party delivered later then planned delivery date.So how can i find that "60 pcs " qty.

 

Thanks in advance 

 

Capture1.JPG

 

 

 

 

 

1 ACCEPTED SOLUTION

@erhan_79 this should be pretty straight forward, see sample attached, I created two table order and order delivered and add delivery qty into two different buckets, you can make the logic change as your model.

 

I would  Kudos if my solution helped. 👉 If you can spend time posting the question, you can also make efforts to give Kudos whoever helped to solve your problem. It is a token of appreciation!



Subscribe to the @PowerBIHowTo YT channel for an upcoming video on List and Record functions in Power Query!!

Learn Power BI and Fabric - subscribe to our YT channel - Click here: @PowerBIHowTo

If my solution proved useful, I'd be delighted to receive Kudos. When you put effort into asking a question, it's equally thoughtful to acknowledge and give Kudos to the individual who helped you solve the problem. It's a small gesture that shows appreciation and encouragement! ❤


Did I answer your question? Mark my post as a solution. Proud to be a Super User! Appreciate your Kudos 🙂
Feel free to email me with any of your BI needs.

View solution in original post

6 REPLIES 6
amitchandak
Super User
Super User

@erhan_79 ,

There should be order no too. But you can have a new column like this in inbound

new column = datediff(inbound[receipt Date],maxx(filter(purchasing, purchasing[material] =inbound[material]),purchasing[planned deilvery date]) ,day)

 

The filter can have an order number also id need may need to have cumulative total

Share with Power BI Enthusiasts: Full Power BI Video (20 Hours) YouTube
Microsoft Fabric Series 60+ Videos YouTube
Microsoft Fabric Hindi End to End YouTube

@erhan_79 this should be pretty straight forward, see sample attached, I created two table order and order delivered and add delivery qty into two different buckets, you can make the logic change as your model.

 

I would  Kudos if my solution helped. 👉 If you can spend time posting the question, you can also make efforts to give Kudos whoever helped to solve your problem. It is a token of appreciation!



Subscribe to the @PowerBIHowTo YT channel for an upcoming video on List and Record functions in Power Query!!

Learn Power BI and Fabric - subscribe to our YT channel - Click here: @PowerBIHowTo

If my solution proved useful, I'd be delighted to receive Kudos. When you put effort into asking a question, it's equally thoughtful to acknowledge and give Kudos to the individual who helped you solve the problem. It's a small gesture that shows appreciation and encouragement! ❤


Did I answer your question? Mark my post as a solution. Proud to be a Super User! Appreciate your Kudos 🙂
Feel free to email me with any of your BI needs.

great @parry2k ;

 

it is working and i got what i need , just one more question pls ;

 

i would like to divide " total order quantity"  / total " on or before " qty .

 

which meausure can i use ? 

@erhan_79 should be easy, as a measure like this

 

Measure = 

DIVIDE( SUM ( Order[Planned Qty] ), SUM ( 'Order Delivered'[Qty] ) )

 

Not sure what you are trying to achieve but you can change the above measure as per your requirement.

 

I would  Kudos if my solution helped. 👉 If you can spend time posting the question, you can also make efforts to give Kudos whoever helped to solve your problem. It is a token of appreciation!



Subscribe to the @PowerBIHowTo YT channel for an upcoming video on List and Record functions in Power Query!!

Learn Power BI and Fabric - subscribe to our YT channel - Click here: @PowerBIHowTo

If my solution proved useful, I'd be delighted to receive Kudos. When you put effort into asking a question, it's equally thoughtful to acknowledge and give Kudos to the individual who helped you solve the problem. It's a small gesture that shows appreciation and encouragement! ❤


Did I answer your question? Mark my post as a solution. Proud to be a Super User! Appreciate your Kudos 🙂
Feel free to email me with any of your BI needs.

@amitchandak  

 

i used your formula , for filter i used order number , but that formula gave me only days and seems like as below 

 

i just wanted to find quantitites , but the new column gaves below days just , minus and positive numbers and same , i think somthing wrong , maybe i could not tell what i wanted 

 

Capture2.JPG

 

 

 

dear @amitchandak 

 

i just only need to calculate and find " 60 " pcs , maybe with a formula a quick measure enough for it ? system will only calculate how many pcs real delivered based on planned delivery date and before for delivery date together.

Helpful resources

Announcements
FabCon and SQLCon Barcelona 2026

FabCon & SQLCon – Barcelona 2026

Join us in Barcelona for FabCon and SQLCon, the Fabric, Power BI, SQL, and AI community event. Save €200 with code FABCMTY200.

60 days of Data Days Carousel

Data Days 2026

Join Fabric Data Days 2026: 60 days of free live/on-demand sessions, challenges, study groups, and certification opportunities.

Power BI DataViz World Championships carousel

Power BI DataViz World Championships - June 2026

A new Power BI DataViz World Championship is coming this June! Don't miss out on submitting your entry.