Hi   I have 2 tables, one is a record of all the received work and another table is all the completed work. Both are linked to a ID list. I can't combine them since some columns do not exist on bot...
  • Fowmy's avatar
    5 years ago

    Xandman 

    You can create three columns in the Received Tables as follows:

    Completed Person = LOOKUPVALUE( Completed[Person] , Completed[Completed ID] , 'Received'[Received ID])

     

    Non Completed Person = 
    IF( ISBLANK(LOOKUPVALUE( Completed[Person] , Completed[Completed ID] , 'Received'[Received ID])), 'Received'[Person] )

     

    Days to Complete = 
    var __date = 
    LOOKUPVALUE( Completed[Date] , Completed[Completed ID] , 'Received'[Received ID])
    return
    IF( __date <> BLANK() , DATEDIFF( 'Received'[Date] , __date , DAY )+1
    )