Hi All ,

 

I am trying to connect to SAP HANA source from PBI desktop and I am getting the following error :

 

 

SAP ERROR.PNG

I am able to preview the data , but it throws error while loading it . Please help with inputs .

 

Thank you.

1 ACCEPTED SOLUTION
v-diye-msft
Community Support
Community Support

Hi @ramkula123 ,

 

If my above post helps, could you please consider Accept it as the solution to help the other members find it more quickly. thanks!

 

Best regards,

Dina Ye

Community Support Team _ Dina Ye
If this post helps, then please consider Accept it as the solution to help the other members find it more
quickly.

View solution in original post

2 REPLIES 2
v-diye-msft
Community Support
Community Support

Hi @ramkula123 ,

 

If my above post helps, could you please consider Accept it as the solution to help the other members find it more quickly. thanks!

 

Best regards,

Dina Ye

Community Support Team _ Dina Ye
If this post helps, then please consider Accept it as the solution to help the other members find it more
quickly.
v-diye-msft
Community Support
Community Support

Hi @ramkula123 

 

It seems related to the memory requirements, generally, to satisfied the memory requirements you should double the amount of data. That means I would provision a server with 128 GB if I have the 64GB instance.

 

You can refer to the blog about sizing HANA databases: https://blogs.sap.com/2017/03/07/the-ultimate-guide-to-effective-sizing-of-sap-hana/

 

Also, here’s another case similar with yours for your reference: https://answers.sap.com/questions/11364223/sap-dbtech-jdbc-4-cannot-allocate-enough-memory-ou.html

 

Tips for avoid the error: https://blogs.sap.com/2014/01/05/6-tips-to-avoid-hana-out-of-memory-oom-errors/

 

Best regards,

Dina Ye

Community Support Team _ Dina Ye
If this post helps, then please consider Accept it as the solution to help the other members find it more
quickly.

Helpful resources

Announcements
September Power BI Update Carousel

Power BI Monthly Update - September 2025

Check out the September 2025 Power BI update to learn about new features.

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.

Top Solution Authors