8 years agoDuration Calculation across days
I have a data set that shows Job Report Dates. I want to calculate basically someone's shift. For the EndofShift I used the Max Job Report Date/Time and then for the BeginningofShift I used the ...
- 8 years ago
You can just have the EndTime subtract StartTime. The result is calculated in days. To get hours, just multiply by 24.
You can also do it with Power Query.
Or you can write an expression like:
=Duration.Hours(Duration.From([EndTime]-[StartTime]))
Regards,
v-sihou-msft
Microsoft Employee
8 years ago
You can just have the EndTime subtract StartTime. The result is calculated in days. To get hours, just multiply by 24.
You can also do it with Power Query.
Or you can write an expression like:
=Duration.Hours(Duration.From([EndTime]-[StartTime]))
Regards,
Deaviouspeanut
2 years agoRegular Visitor
With the duration.hours, How do I make it not respond -16 when the hours are 4pm to 12am which should be 8