Determining Manufacturing Schedule Loaded per cell

I have a very simple Data Source that tells me the Job, Start Date, Cell it will be manufactured on, and the estimated hours. I need to aggregate this Data into a simple calendar of Total hours by cell by Day. Is this possible? Thanks in advance

 

Jobs Table

Job NumberCellPart #JobStartDateEstHours
1234a1x1239/3/202117.5
998b1x5579/3/202123
887c23wec9/1/20217
665d23det9/2/202111

 

I am guessing this would be the first intermediate Step??

Job NumberCell9/1/20219/2/20219/3/20219/4/20219/5/20219/6/20219/7/2021
1234a1  8 Skip WE Skip WE81.5
998b1  8 Skip WE Skip WE87
887c27   Skip WE Skip WE  
665d2 83 Skip WE Skip WE  

 

Final Desired Result:

Cell9/1/20219/2/20219/3/20219/6/20219/7/2021
1  16161.5
278387
  • Anonymous's avatar
    Anonymous
    5 years ago

    Hi bkwohls,

    You can create a new table as calendar to store the date values based on the raw table, then write a measure to calculate datediff between the start date and the calendar date to get daily work hours.

    After these steps, you can use the raw table category and new table date, measure to create the matrix visuals.

    Sample formulas:

    Calculated table.

    Calendar = 
    CALENDAR (
        MINX ( 'Table', [JobStartDate] ),
        MAXX ( 'Table', [JobStartDate] ) + 365
    )

    Measure:

    Measure = 
    VAR totalHour =
        CALCULATE (
            SUM ( 'Table'[EstHours] ),
            ALLSELECTED ( 'Table' ),
            VALUES ( 'Table'[Job Number] ),
            VALUES ( 'Table'[Part #] )
        )
    VAR cDate =
        MAX ( 'Calendar'[Date] )
    VAR jobStart =
        CALCULATE (
            MAX ( 'Table'[JobStartDate] ),
            ALLSELECTED ( 'Table' ),
            VALUES ( 'Table'[Job Number] ),
            VALUES ( 'Table'[Part #] )
        )
    RETURN
        IF (
            HASONEVALUE ( 'Table'[Job Number] ),
            IF (
                cDate >= jobStart
                    && WEEKDAY ( cDate, 2 ) <= 5,
                VAR diff =
                    totalHour
                        - (
                            COUNTROWS (
                                FILTER ( CALENDAR ( jobStart, cDate ), WEEKDAY ( [Date], 2 ) <= 5 )
                            ) - 1
                        ) * 8
                RETURN
                    IF ( diff >= 0, MIN ( MAX ( diff, 0 ), 8 ) )
            )
        )

    Result:

    Regards,
    Xiaoxin Sheng

5 Replies

    • bkwohls's avatar
      bkwohls
      Helper I

      My data source for Jobs data only provides me with a Start Date and a Estimate number of hours to complete the Job. Based on an 8 hour day and skipping weekends I want to be able to calculate how amny hours per day I have in teh Job Schedule.

  • Anonymous's avatar
    Anonymous
    Not applicable

    Hi bkwohls,

    It seems like a common analysis requirement about two date fields, you can take a look at the following link start/end dagte part if help:

    Before You Post, Read This 

    In addition, you can also try to create a new table to expand and the date ranges and link to raw table records then you can simply aggregate these records from the date ranges:

    Solved: Spread revenue across period based on start and en... - Microsoft Power BI Community

    Regards,

    Xiaoxin Sheng

    • bkwohls's avatar
      bkwohls
      Helper I

      I only have a start date and then the hours that are estimated. I am essentially trying to calculate an end date based on an 8 hour work day given the Start date and hours required. With that info then I can aggregate all the hours per day and evaluate resource load per day per manufacturing cell.

       

      • Anonymous's avatar
        Anonymous
        Not applicable

        Hi bkwohls,

        You can create a new table as calendar to store the date values based on the raw table, then write a measure to calculate datediff between the start date and the calendar date to get daily work hours.

        After these steps, you can use the raw table category and new table date, measure to create the matrix visuals.

        Sample formulas:

        Calculated table.

        Calendar = 
        CALENDAR (
            MINX ( 'Table', [JobStartDate] ),
            MAXX ( 'Table', [JobStartDate] ) + 365
        )

        Measure:

        Measure = 
        VAR totalHour =
            CALCULATE (
                SUM ( 'Table'[EstHours] ),
                ALLSELECTED ( 'Table' ),
                VALUES ( 'Table'[Job Number] ),
                VALUES ( 'Table'[Part #] )
            )
        VAR cDate =
            MAX ( 'Calendar'[Date] )
        VAR jobStart =
            CALCULATE (
                MAX ( 'Table'[JobStartDate] ),
                ALLSELECTED ( 'Table' ),
                VALUES ( 'Table'[Job Number] ),
                VALUES ( 'Table'[Part #] )
            )
        RETURN
            IF (
                HASONEVALUE ( 'Table'[Job Number] ),
                IF (
                    cDate >= jobStart
                        && WEEKDAY ( cDate, 2 ) <= 5,
                    VAR diff =
                        totalHour
                            - (
                                COUNTROWS (
                                    FILTER ( CALENDAR ( jobStart, cDate ), WEEKDAY ( [Date], 2 ) <= 5 )
                                ) - 1
                            ) * 8
                    RETURN
                        IF ( diff >= 0, MIN ( MAX ( diff, 0 ), 8 ) )
                )
            )

        Result:

        Regards,
        Xiaoxin Sheng