Determining Manufacturing Schedule Loaded per cell
- Anonymous5 years ago
Hi bkwohls,
You can create a new table as calendar to store the date values based on the raw table, then write a measure to calculate datediff between the start date and the calendar date to get daily work hours.
After these steps, you can use the raw table category and new table date, measure to create the matrix visuals.
Sample formulas:
Calculated table.
Calendar = CALENDAR ( MINX ( 'Table', [JobStartDate] ), MAXX ( 'Table', [JobStartDate] ) + 365 )Measure:
Measure = VAR totalHour = CALCULATE ( SUM ( 'Table'[EstHours] ), ALLSELECTED ( 'Table' ), VALUES ( 'Table'[Job Number] ), VALUES ( 'Table'[Part #] ) ) VAR cDate = MAX ( 'Calendar'[Date] ) VAR jobStart = CALCULATE ( MAX ( 'Table'[JobStartDate] ), ALLSELECTED ( 'Table' ), VALUES ( 'Table'[Job Number] ), VALUES ( 'Table'[Part #] ) ) RETURN IF ( HASONEVALUE ( 'Table'[Job Number] ), IF ( cDate >= jobStart && WEEKDAY ( cDate, 2 ) <= 5, VAR diff = totalHour - ( COUNTROWS ( FILTER ( CALENDAR ( jobStart, cDate ), WEEKDAY ( [Date], 2 ) <= 5 ) ) - 1 ) * 8 RETURN IF ( diff >= 0, MIN ( MAX ( diff, 0 ), 8 ) ) ) )Result:
Regards,
Xiaoxin Sheng
Hi bkwohls,
It seems like a common analysis requirement about two date fields, you can take a look at the following link start/end dagte part if help:
In addition, you can also try to create a new table to expand and the date ranges and link to raw table records then you can simply aggregate these records from the date ranges:
Solved: Spread revenue across period based on start and en... - Microsoft Power BI Community
Regards,
Xiaoxin Sheng
- bkwohls5 years agoHelper I
I only have a start date and then the hours that are estimated. I am essentially trying to calculate an end date based on an 8 hour work day given the Start date and hours required. With that info then I can aggregate all the hours per day and evaluate resource load per day per manufacturing cell.
- Anonymous5 years agoNot applicable
Hi bkwohls,
You can create a new table as calendar to store the date values based on the raw table, then write a measure to calculate datediff between the start date and the calendar date to get daily work hours.
After these steps, you can use the raw table category and new table date, measure to create the matrix visuals.
Sample formulas:
Calculated table.
Calendar = CALENDAR ( MINX ( 'Table', [JobStartDate] ), MAXX ( 'Table', [JobStartDate] ) + 365 )Measure:
Measure = VAR totalHour = CALCULATE ( SUM ( 'Table'[EstHours] ), ALLSELECTED ( 'Table' ), VALUES ( 'Table'[Job Number] ), VALUES ( 'Table'[Part #] ) ) VAR cDate = MAX ( 'Calendar'[Date] ) VAR jobStart = CALCULATE ( MAX ( 'Table'[JobStartDate] ), ALLSELECTED ( 'Table' ), VALUES ( 'Table'[Job Number] ), VALUES ( 'Table'[Part #] ) ) RETURN IF ( HASONEVALUE ( 'Table'[Job Number] ), IF ( cDate >= jobStart && WEEKDAY ( cDate, 2 ) <= 5, VAR diff = totalHour - ( COUNTROWS ( FILTER ( CALENDAR ( jobStart, cDate ), WEEKDAY ( [Date], 2 ) <= 5 ) ) - 1 ) * 8 RETURN IF ( diff >= 0, MIN ( MAX ( diff, 0 ), 8 ) ) ) )Result:
Regards,
Xiaoxin Sheng