Determining Current Project Phase after previous was phase was completed

Hello,

 

I am trying to determine the current phase of a project after it's preceding phase was completed. The order of phases goes from Planning, Idea, Development & Qualification. I want to be able to show that Planning is the next phase and to filter out Idea, which was already completed and both Dev & Qual that haven't occurred until Planning is complete. Please see the dataset below for reference. Thank you all for the help.

 

Project NamePhaseMilestonesBaseline FinishPhase #Phase End (Baseline)Phase End (LBE)Phase End (Actual)Phase Sort Table.OrderMilestone Binary StatusMilestone StatusCompleted Milestones
BlossomIdeaIDEA Phase End11/18/2020111/18/202011/18/202011/18/202011CompleteIDEA Phase End
BlossomPlanningPLANNING Phase End08/01/2022208/01/202208/01/2022 20Upcoming 
BlossomDevelopmentDEVELOPMENT Phase End06/12/2023306/12/202306/12/2023 30Upcoming 
BlossomQualificationQUALIFICATION Phase End11/14/2024411/14/202411/14/2024 40Upcoming