Hi all,

 

I am trying to calculate delta x between two curves: x2 - x1. The final result should be an amount of days.
The dates are stored in the column Cycles[Cycle End Date] and the percentage is calculated using measures Progress BL and ProgressActuals.

 

ProgressBL = CALCULATE([Weight In Scope],FILTER(ALL('Cycles'),'Cycles'[Cycle End Date]<=MAX('Cycles'[Cycle End Date])), FILTER('Time Registration', 'Time Registration'[Time Path] = "Baseline - Project"))
ProgressActuals = CALCULATE([Weight In Scope],FILTER(ALL('Cycles'),'Cycles'[Cycle End Date]<=MAX('Cycles'[Cycle End Date])), FILTER('Time Registration', 'Time Registration'[Time Path] = "Actuals - Critical"))

However, I got stuck here and don't know how to continue and calculate delta x. Delta x should be calculated for every date until the max cycle date of Progress Actuals.

curves.png

 

I want to create a histogram where x axis is dates and y axis is the number of days (delta x).

 

So, how could I calculate this delta x? Maybe there is another way how to do it?

Thank you!

 

 

2 REPLIES 2
v-yulgu-msft
Microsoft Employee
Microsoft Employee

Hi @mkr,

 

What is the calculation syntax for delta x in your scenario? It would be better to post some dummy dataset. Also, what is the formula for [Weight In Scope]?

 

Regards,

Yuliana Gu

Community Support Team _ Yuliana Gu
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

Hi Yuliana,

 

I was trying to calculate two dates: 1. from Baseline - Project, 2. from Actuals -Critical, where the progress percentage is the same.  At the end I want to find the difference in days between two curves. I want to plot dates on x axis and number of days (delta x) on y axis. Maybe there is another, better way how to get the final result.

The measure [Weight In Scope] is a measure in Azure Analysis Service and the value is assigned when certain criteria are met. Link contains Excel and Power BI files.

 

Excel and PowerBI file

 

Thank you!

Marija

Helpful resources

Announcements
New to Fabric survey Carousel

New to Fabric Survey

If you have recently started exploring Fabric, we'd love to hear how it's going. Your feedback can help with product improvements.

Power BI DataViz World Championships carousel

Power BI DataViz World Championships - June 2026

A new Power BI DataViz World Championship is coming this June! Don't miss out on submitting your entry.

Join our Fabric User Panel

Join our Fabric User Panel

Share feedback directly with Fabric product managers, participate in targeted research studies and influence the Fabric roadmap.

March Power BI Update Carousel

Power BI Community Update - March 2026

Check out the March 2026 Power BI update to learn about new features.