Could someone point out where I have gone wrong here. I have 'days since last update' which gives me actual days between A and B but I want to also have working days to exlude weekends. I have used NETWORKDAYS to count the working days (Mon-Fri).
The Networkdays() counts both the start and end days, if they are working days and the calculation is correct. If you want to exclude the start date , use start date+1 or if you want to exclude today, use today()-1 as the end date
Hope this helps
2 Replies
- Padycosmos
Solution Sage
The Networkdays() counts both the start and end days, if they are working days and the calculation is correct. If you want to exclude the start date , use start date+1 or if you want to exclude today, use today()-1 as the end date
Hope this helps
- richrich123
Helper III