Forum Discussion
sameergupta60
3 years agoHelper IV
Dax Help
Hi Team If my RCC level is on R07 then my BW should start if it started showing 1, or not showing zero in another column we need dax for the above querry attaching excel with data Case 1 ...
sameergupta60
3 years agoHelper IV
thanks for your support,
but my query is if my RCC is on R07 then block work should start date ideally.
if block work has not started at with respective RCC floor r07 then it should be 0 or 1.
ryan_mayu
3 years agoSuper User
could you pls provide the sample data which includes different cases and the expected output based on that?
- sameergupta603 years agoHelper IV
hi
ā
- sameergupta603 years agoHelper IV
suppose my blockwork start date is 10 Oct 22 then it will reflect near to R07 level in the Blockwork table.