Forum Discussion
sameergupta60
3 years agoHelper IV
Dax Help
Hi Team If my RCC level is on R07 then my BW should start if it started showing 1, or not showing zero in another column we need dax for the above querry attaching excel with data Case 1 ...
ryan_mayu
3 years agoSuper User
not clear about your question
Could you pls explain more on this? or what's your excel formula?
- sameergupta603 years agoHelper IV
hi,
My query is if my RCC level is on r07 then my block work has to start date .
but if my BW start date is not started at any level then it is 0 or 1.
for that, we need dax or measure.
Regards,
Sameer Gupta
- ryan_mayu3 years agoSuper User
is the BW column the expected output?
- sameergupta603 years agoHelper IV
yes