Date Time + 12 Work Hours (Operational Hours)

Hello Everyone,

 

I need to add 12 Work Hours (aka. Operational Hours) to a Date Time value.

My Day Start is 06:00:00 and Day End is 18:00:00, I need to exclude Weekends and Public Holidays.

 

How would i write the M Code/Power Query calculated column to do this?

(ie. how to i create the "Start+12WorkHours" column in the below example) 

 

thank you

 

Example Data:

Work Hours Table

Start TimeEnd Time
6:00:0018:00:00

 

Holidays List (Holidays)

Date
1/01/2018
26/01/2018
5/03/2018

 

Data Table (Data)

 

Start                 Start+12WorkHours Notes
5/02/2018 10:006/02/2018 10:00Work Day is 6AM-6PM. So +12 Work hours is next day at same time
6/02/2018 4:007/02/2018 6:0004:00:00 is before the work day starts (6AM). So + 12 Work hours from 06/02/2018 6AM is 07/02/2018 6AM
6/02/2018 19:007/02/2018 18:0019:00:00 is after the work day finishes (6PM). So + 12 Work hours from 07/02/2018 6AM is 07/02/2018 6PM
2/02/2018 17:005/02/2018 17:0002/02/2018 is a Friday, so need to skip over the weekend to monday's date 05/02/2018
29/12/2017 17:00 2/01/2018 17:0029/12/2017 is a Friday and 01/01/2018 is a Public Holiday, so need to skip to Tuesday 02/01/2018

 