DATEDIFF Working Days
- 9 years ago
Hi Benjamin_500,
First you should create a holiday table including all holiday form Delivery start date to Today. Then create relationship between holiday table and your 'Repot' table.
I try to reproduce your scenario using date from 2017/1/1 to 2017/3/31.
Search the holiday days for 2017, I use "List of federal Public Holidays of USA in 2017", and type it in Power BI table as followings.
Create relationship between Holiday table and Date Table.
Use WEEKDAY function to get weekdays, use RELATED function to get holidays. Use if function to decide if the day is work day.WeekDay = WEEKDAY(DateTable[Date]) Holiday = RELATED(Holiday[Holiday])
If work day = IF(OR(DateTable[WeekDay]=1,DateTable[WeekDay]=7),0,IF(ISBLANK(DateTable[Holiday]),1,0))
The 1 stands for the day is work day.
Finally, create a measure to calculate the number od holidays. And create a card visual to display the result.Total work days = CALCULATE(COUNT(DateTable[Date]),FILTER(DateTable,DateTable[If work day]=1))
If you have other issues, please let me know.Best Regards,
Angelia
Hi Benjamin_500,
First you should create a holiday table including all holiday form Delivery start date to Today. Then create relationship between holiday table and your 'Repot' table.
I try to reproduce your scenario using date from 2017/1/1 to 2017/3/31.
Search the holiday days for 2017, I use "List of federal Public Holidays of USA in 2017", and type it in Power BI table as followings.
Create relationship between Holiday table and Date Table.
Use WEEKDAY function to get weekdays, use RELATED function to get holidays. Use if function to decide if the day is work day.
WeekDay = WEEKDAY(DateTable[Date]) Holiday = RELATED(Holiday[Holiday])
If work day = IF(OR(DateTable[WeekDay]=1,DateTable[WeekDay]=7),0,IF(ISBLANK(DateTable[Holiday]),1,0))
The 1 stands for the day is work day.
Finally, create a measure to calculate the number od holidays. And create a card visual to display the result.
Total work days = CALCULATE(COUNT(DateTable[Date]),FILTER(DateTable,DateTable[If work day]=1))
If you have other issues, please let me know.
Best Regards,
Angelia
v-huizhn-msft wrote:Hi Benjamin_500,
First you should create a holiday table including all holiday form Delivery start date to Today. Then create relationship between holiday table and your 'Repot' table.
I try to reproduce your scenario using date from 2017/1/1 to 2017/3/31.
Search the holiday days for 2017, I use "List of federal Public Holidays of USA in 2017", and type it in Power BI table as followings.
Create relationship between Holiday table and Date Table.
Use WEEKDAY function to get weekdays, use RELATED function to get holidays. Use if function to decide if the day is work day.
WeekDay = WEEKDAY(DateTable[Date]) Holiday = RELATED(Holiday[Holiday])
If work day = IF(OR(DateTable[WeekDay]=1,DateTable[WeekDay]=7),0,IF(ISBLANK(DateTable[Holiday]),1,0))
The 1 stands for the day is work day.
Finally, create a measure to calculate the number od holidays. And create a card visual to display the result.Total work days = CALCULATE(COUNT(DateTable[Date]),FILTER(DateTable,DateTable[If work day]=1))
If you have other issues, please let me know.Best Regards,
Angelia
Hi v-huizhn-msft Angelia,
I'm having the same issue, your solution is great, however this will give the total result for an year. how to obtain work days per month basis. i.e.
January 20
Feb 19
Mar 21 likwise. I'm bit strugglling with dax code. Thanks again. Keep up the good work!