Forum Discussion
tanct
8 years agoRegular Visitor
Cumulative Weekday
Dear All, Could you please share what is the Dax code for the cumulative working day for the following condition below:- 1. First working day of the month assigned as 1, then cumulative ad...
- 8 years ago
Hi tanct,
Try this calculated column formula
=CALCULATE(COUNTROWS('DIM-Calendar'),FILTER('DIM-Calendar','DIM-Calendar'[Date]<=EARLIER('DIM-Calendar'[Date])&&'DIM-Calendar'[Date]>=EARLIER([Date])-DAY(EARLIER([Date]))+1&&'DIM-Calendar'[Weekend]=1))Hope this helps.
- 8 years ago
You can also try to create a calculated column with following formula.
Cumulative Weekday = CALCULATE ( SUM ( 'DIM-Calendar'[Weekend] ), FILTER ( 'DIM-Calendar', 'DIM-Calendar'[Date] <= EARLIER ( 'DIM-Calendar'[Date] ) && 'DIM-Calendar'[Year] = EARLIER ( 'DIM-Calendar'[Year] ) && 'DIM-Calendar'[Month] = EARLIER ( 'DIM-Calendar'[Month] ) ) )Best Regards,
Herbert
Zubair_Muhammad
8 years agoCommunity Champion
Hi tanct
Shouldn't 04.07.2016 be = 2 (second working day)
Could you share file via onedrive or google drive?
Give this code a try for the time being
=
CALCULATE (
SUM ( 'Dim-Calendar'[Weekend] ),
FILTER (
'Dim-Calendar',
'Dim-Calendar'[Day] <= EARLIER ( 'Dim-Calendar'[Day] )
&& 'Dim-Calendar'[Month] = EARLIER ( 'Dim-Calendar'[Month] )
&& 'Dim-Calendar'[Month] = EARLIER ( 'Dim-Calendar'[Month] )
)
)
tanct
8 years agoRegular Visitor
Hi,
Thanks, please find the below link for the PBIX:-
https://drive.google.com/open?id=1V4bOPU8VHJ8B3C_GE9NQlyKpqEX7Md09
You may go to table DIM Calendar.
Basically, I have identified the weekend for each of the month (in column Weekend), just pending to sum up the computed weekend figure to arrive working day of the month. Thanks in advance.
- Ashish_Mathur8 years agoSuper User
Hi tanct,
Try this calculated column formula
=CALCULATE(COUNTROWS('DIM-Calendar'),FILTER('DIM-Calendar','DIM-Calendar'[Date]<=EARLIER('DIM-Calendar'[Date])&&'DIM-Calendar'[Date]>=EARLIER([Date])-DAY(EARLIER([Date]))+1&&'DIM-Calendar'[Weekend]=1))Hope this helps.