Cumulative Budget Starting at Zero
I am trying to put together a visual for cumulative spend over time on a project. So far I have been able to get a chart based on actuals, but would like to have spend start at zero rather than the first transaction. Some details for context:
- 'Fusion Project Actuals' --> This table contains details on actual project transactions, with the following relevant variables:
- 'Fusion Project Actuals'[Accounting Date] --> Gives the date for each specific transaction within a project
- 'Fusion Project Actuals'[Amount] --> The amount of spend on each transaction for a specific project
- 'Fusion Project Details' --> This table gives project details primarily revolving around budget
- 'Fusion Project Details'[Project Start Date] --> This is the date a project was opened, BEFORE the first transaction ([Accounting Date]) (i.e., actual spend at this date is always zero)
- For the visual, I created a measure to track cumulative spend based off [Amount] (X axis uses Accounting Date, Y axis uses Amount). The code for the measure is as follows:
Cumulative Total Spend =
VAR MaxDate = MAX('Fusion Project Actuals'[Accounting Date])
VAR Result =
CALCULATE(
SUM('Fusion Project Actuals'[Amount]),
'Fusion Project Actuals'[Accounting Date] <= MaxDate,
ALL ('Fusion Project Actuals'[Accounting Date]))
RETURN
Result
------------------------------------------------------------------------------------------
The graph returns cumulative spend correctly, but I would like to have it begin with zero at [Project Start Date] on the x axis, rather than the first [Amount] at [Accounting Date]. Any help is much appreciated. Thanks!
3 Replies
- amitchandak
Super User
Anonymous , try a mesure like , assumed you have project or project id
Cumulative Total Spend =
VAR MaxDate = MAX('Fusion Project Actuals'[Accounting Date]
RETURN
CALCULATE(
SUM('Fusion Project Actuals'[Amount]),
filter( ALL ('Fusion Project Actuals'[Accounting Date]) ,'Fusion Project Actuals'[Accounting Date] <= MaxDate
&& 'Fusion Project Actuals'[project] = max( 'Fusion Project Actuals'[project] )
))Please provide your feedback comments and advice for new videos
Tutorial Series Dax Vs SQL Direct Query PBI Tips
Appreciate your Kudos.- AnonymousNot applicable
For some reason PBI won't recognize my first reference to Project Number. For reference, this variable is stored in text format because the id's are formatted as "S12345"
- AnonymousNot applicable
amitchandak -- to try and achieve this, I have created a new table called 'Fusion Project Actuals - Cumulative' that contains the fields Project Number, Transaction Date, Task Number, Amount. For each project number, there is now a row in this table that contains a transaction date as start date, and a first amount of zero. So the data is in there, but still having trouble getting the graphic to appear correctly. My code is currently as follows:
Cumulative Total Spend =VAR MaxDate = MAX('Fusion Project Actuals - Cumulative'[Transaction Date])VAR Result =CALCULATE(SUM('Fusion Project Actuals - Cumulative'[Amount]),'Fusion Project Actuals - Cumulative'[Transaction Date] <= MaxDate,ALL ('Fusion Project Actuals - Cumulative'[Transaction Date]))RETURNResultAny ideas?? Thanks.