I am trying to put together a visual for cumulative spend over time on a project. So far I have been able to get a chart based on actuals, but would like to have spend start at zero rather than the first transaction. Some details for context:
Cumulative Total Spend =
VAR MaxDate = MAX('Fusion Project Actuals'[Accounting Date])
VAR Result =
CALCULATE(
SUM('Fusion Project Actuals'[Amount]),
'Fusion Project Actuals'[Accounting Date] <= MaxDate,
ALL ('Fusion Project Actuals'[Accounting Date]))
RETURN
Result
------------------------------------------------------------------------------------------
The graph returns cumulative spend correctly, but I would like to have it begin with zero at [Project Start Date] on the x axis, rather than the first [Amount] at [Accounting Date]. Any help is much appreciated. Thanks!
@Anonymous , try a mesure like , assumed you have project or project id
Cumulative Total Spend =
VAR MaxDate = MAX('Fusion Project Actuals'[Accounting Date]
RETURN
CALCULATE(
SUM('Fusion Project Actuals'[Amount]),
filter( ALL ('Fusion Project Actuals'[Accounting Date]) ,'Fusion Project Actuals'[Accounting Date] <= MaxDate
&& 'Fusion Project Actuals'[project] = max( 'Fusion Project Actuals'[project] )
))
Please provide your feedback comments and advice for new videos
Tutorial Series Dax Vs SQL Direct Query PBI Tips
Appreciate your Kudos.
@amitchandak -- to try and achieve this, I have created a new table called 'Fusion Project Actuals - Cumulative' that contains the fields Project Number, Transaction Date, Task Number, Amount. For each project number, there is now a row in this table that contains a transaction date as start date, and a first amount of zero. So the data is in there, but still having trouble getting the graphic to appear correctly. My code is currently as follows:
For some reason PBI won't recognize my first reference to Project Number. For reference, this variable is stored in text format because the id's are formatted as "S12345"
This is your chance to engage directly with the engineering team behind Fabric and Power BI. Share your experiences and shape the future.
Check out the June 2025 Power BI update to learn about new features.
User | Count |
---|---|
76 | |
76 | |
56 | |
38 | |
34 |
User | Count |
---|---|
99 | |
56 | |
51 | |
44 | |
40 |