Creating a date spread table for activities and resource

Hi

 

I've been trying to figure this out for too long and need some help.

 

I have a database containing activity data with multiple resources assigned per activity, Each row contains Activity ID, Resource Name, Start, Finish, Budget Hrs.

 

I'm trying to plot the resource over time and want to create a calendar table holding the value per activity/resource of each period throughout the duration of the activities.

 

The source data looks like this:

Activity ID

Resource

Start

Finish

Budget

ACT001

Jane

01-Jan-21

28-Feb-21

100

ACT001

Dave

01-Jan-21

31-Mar-21

100

ACT002

Jane

01-Mar-21

31-Apr-21

20

ACT003

Bob

01-Feb-21

31-Apr-21

75

 

I started with a DAX formula that creates a min/max date spread showing the start of each month.

 

SPREAD_DATES = FILTER (
CALENDAR(MIN('RESOURCE'[start]),MAX('RESOURCE'[finish])),
EOMONTH ( [Date],-1 )+1 = [Date]

 

But what I need is a table that has repeat periods where activities/resource overlap.

 

So the table should look like this:

 

Period Start Date

Activity ID

Resource

Budget

01-Jan-21

ACT001

Jane

50

01-Jan-21

ACT001

Dave

33

01-Feb-21

ACT001

Jane

50

01-Feb-21

ACT001

Dave

33

01-Feb-21

ACT003

Bob

25

01-Mar-21

ACT001

Dave

33

01-Mar-21

ACT002

Jane

10

01-Mar-21

ACT003

Bob

25

01-Apr-21

ACT002

Jane

10

01-Apr-21

ACT003

Bob

25

 

Any help or suggestions appreciated.

 

Thanks in advance.

Matt

 

 

  • Hi, spuff55 

    Sorry for late reply. You can create a Calculated table and a Calculated column to get the result you want.

     

    1 Calculated table

    Table =
    
    VAR cal =
    
        SELECTCOLUMNS (
    
            FILTER (
    
                CALENDAR ( MIN ( RESOURCE[Start] ), MAX ( RESOURCE[Finish] ) ),
    
                DAY ( [Date] ) = 1
    
            ),
    
            "Period", [Date]
    
        )
    
    VAR cross_t =
    
        FILTER (
    
            CROSSJOIN ( RESOURCE, cal ),
    
            [Period] >= RESOURCE[Start]
    
                && [Period] <= RESOURCE[Finish]
    
        )
    
    VAR sel_t =
    
        SELECTCOLUMNS (
    
            cross_t,
    
            "Period Start Date", [Period],
    
            "ActivityID", [Activity ID],
    
            "Resource", [Recource],
    
            "Budget_overall", [Budget]
    
        )
    
    RETURN
    
        sel_t
    
    
    
    
    
    2 Calculated column
    
    Budget =
    
    VAR num =
    
        CALCULATE (
    
            COUNT ( 'Table'[Budget_overall] ),
    
            ALLEXCEPT ( 'Table', 'Table'[ActivityID], 'Table'[Resource] )
    
        )
    
    RETURN
    
        'Table'[Budget_overall] / num

     

     

    The result looks like this:

     

     

    Here is the pbix.

     

    Best Regards,

    Caiyun Zheng

     

6 Replies

  • v-cazheng-msft's avatar
    v-cazheng-msft
    Icon for Community Support rankCommunity Support

    Hi, spuff55 

    You can create a Calculated table to get the result you want.

     

    New_table =
    
    VAR start1 =
    
        CALCULATE (
    
            SELECTEDVALUE ( RESOURCE[Start] ),
    
            RESOURCE[Activity ID] = "ACT001",
    
            RESOURCE[Recource] = "Dave"
    
        )
    
    VAR finish1 =
    
        CALCULATE (
    
            SELECTEDVALUE ( RESOURCE[Finish] ),
    
            RESOURCE[Activity ID] = "ACT001",
    
            RESOURCE[Recource] = "Dave"
    
        )
    
    VAR mon_inter1 =
    
        MONTH ( finish1 ) - MONTH ( start1 ) + 1
    
    VAR t1 =
    
        SELECTCOLUMNS (
    
            FILTER ( CALENDAR ( start1, finish1 ), DAY ( [Date] ) = 1 ),
    
            "Period Start Date", [Date]
    
        )
    
    VAR tt1 =
    
        ADDCOLUMNS (
    
            t1,
    
            "ActivityID", "ACT001",
    
            "Resource", "Dave",
    
            "Budget",
    
                FORMAT (
    
                    DIVIDE (
    
                        CALCULATE (
    
                            SELECTEDVALUE ( RESOURCE[Budget] ),
    
                            RESOURCE[Activity ID] = "ACT001",
    
                            RESOURCE[Recource] = "Dave"
    
                        ),
    
                        mon_inter1
    
                    ),
    
                    "#"
    
                )
    
        )
    
    VAR start2 =
    
        CALCULATE (
    
            SELECTEDVALUE ( RESOURCE[Start] ),
    
            RESOURCE[Activity ID] = "ACT001",
    
            RESOURCE[Recource] = "Jane"
    
        )
    
    VAR finish2 =
    
        CALCULATE (
    
            SELECTEDVALUE ( RESOURCE[Finish] ),
    
            RESOURCE[Activity ID] = "ACT001",
    
            RESOURCE[Recource] = "Jane"
    
        )
    
    VAR mon_inter2 =
    
        MONTH ( finish2 ) - MONTH ( start2 ) + 1
    
    VAR t2 =
    
        SELECTCOLUMNS (
    
            FILTER ( CALENDAR ( start2, finish2 ), DAY ( [Date] ) = 1 ),
    
            "Period Start Date", [Date]
    
        )
    
    VAR tt2 =
    
        ADDCOLUMNS (
    
            t2,
    
            "ActivityID", "ACT001",
    
            "Resource", "Jane",
    
            "Budget",
    
                FORMAT (
    
                    DIVIDE (
    
                        CALCULATE (
    
                            SELECTEDVALUE ( RESOURCE[Budget] ),
    
                            RESOURCE[Activity ID] = "ACT001",
    
                            RESOURCE[Recource] = "Jane"
    
                        ),
    
                        mon_inter2
    
                    ),
    
                    "#"
    
                )
    
        )
    
    VAR start3 =
    
        CALCULATE (
    
            SELECTEDVALUE ( RESOURCE[Start] ),
    
            RESOURCE[Activity ID] = "ACT002",
    
            RESOURCE[Recource] = "Jane"
    
        )
    
    VAR finish3 =
    
        CALCULATE (
    
            SELECTEDVALUE ( RESOURCE[Finish] ),
    
            RESOURCE[Activity ID] = "ACT002",
    
            RESOURCE[Recource] = "Jane"
    
        )
    
    VAR mon_inter3 =
    
        MONTH ( finish3 ) - MONTH ( start3 ) + 1
    
    VAR t3 =
    
        SELECTCOLUMNS (
    
            FILTER ( CALENDAR ( start3, finish3 ), DAY ( [Date]) = 1 ),
    
            "Period Start Date", [Date]
    
        )
    
    VAR tt3 =
    
        ADDCOLUMNS (
    
            t3,
    
            "ActivityID", "ACT002",
    
            "Resource", "Jane",
    
            "Budget",
    
                FORMAT (
    
                    DIVIDE (
    
                        CALCULATE (
    
                            SELECTEDVALUE ( RESOURCE[Budget] ),
    
                            RESOURCE[Activity ID] = "ACT002",
    
                            RESOURCE[Recource] = "Jane"
    
                        ),
    
                        mon_inter3
    
                    ),
    
                    "#"
    
                )
    
        )
    
    VAR start4 =
    
        CALCULATE (
    
            SELECTEDVALUE ( RESOURCE[Start] ),
    
            RESOURCE[Activity ID] = "ACT003",
    
            RESOURCE[Recource] = "Bob"
    
        )
    
    VAR finish4 =
    
        CALCULATE (
    
            SELECTEDVALUE ( RESOURCE[Finish] ),
    
            RESOURCE[Activity ID] = "ACT003",
    
            RESOURCE[Recource] = "Bob"
    
        )
    
    VAR mon_inter4 =
    
        MONTH ( finish4 ) - MONTH ( start4 ) + 1
    
    VAR t4 =
    
        SELECTCOLUMNS (
    
            FILTER ( CALENDAR ( start4, finish4 ), DAY ( [Date] ) = 1 ),
    
            "Period Start Date", [Date]
    
        )
    
    VAR tt4 =
    
        ADDCOLUMNS (
    
            t4,
    
            "ActivityID", "ACT003",
    
            "Resource", "Bob",
    
            "Budget",
    
                FORMAT (
    
                    DIVIDE (
    
                        CALCULATE (
    
                            SELECTEDVALUE ( RESOURCE[Budget] ),
    
                            RESOURCE[Activity ID] = "ACT003",
    
                            RESOURCE[Recource] = "Bob"
    
                        ),
    
                        mon_inter4
    
                    ),
    
                    "#"
    
                )
    
        )
    
    RETURN
    
        UNION ( tt1, tt2, tt3, tt4 )
    
    

    The result looks like this:

     

     

    Here is the pbix file.

     

    Best Regards,

    Caiyun Zheng

     

    Is that the answer you're looking for? If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

     

     

    • spuff55's avatar
      spuff55
      Frequent Visitor

      Hi Caiyun

       

      That's really great, but although it provides the end result, I didn't mention that the original table is being driven by a project management tool and is always changing as new resource assignement and tasks are added.

       

      Would there be a way to do the same thing without explicitly listing the names within the DAX so that new additions to the list are accounted for in the second table.

       

      e.g. I added "Danny" to the first table and his task isn't calculated in the second.

       

       

      Thank you for taking the time to answer, and for your jedi level solution.

       

      Matt

       

      • v-cazheng-msft's avatar
        v-cazheng-msft
        Icon for Community Support rankCommunity Support

        Hi, spuff55 

        Sorry for late reply. You can create a Calculated table and a Calculated column to get the result you want.

         

        1 Calculated table

        Table =
        
        VAR cal =
        
            SELECTCOLUMNS (
        
                FILTER (
        
                    CALENDAR ( MIN ( RESOURCE[Start] ), MAX ( RESOURCE[Finish] ) ),
        
                    DAY ( [Date] ) = 1
        
                ),
        
                "Period", [Date]
        
            )
        
        VAR cross_t =
        
            FILTER (
        
                CROSSJOIN ( RESOURCE, cal ),
        
                [Period] >= RESOURCE[Start]
        
                    && [Period] <= RESOURCE[Finish]
        
            )
        
        VAR sel_t =
        
            SELECTCOLUMNS (
        
                cross_t,
        
                "Period Start Date", [Period],
        
                "ActivityID", [Activity ID],
        
                "Resource", [Recource],
        
                "Budget_overall", [Budget]
        
            )
        
        RETURN
        
            sel_t
        
        
        
        
        
        2 Calculated column
        
        Budget =
        
        VAR num =
        
            CALCULATE (
        
                COUNT ( 'Table'[Budget_overall] ),
        
                ALLEXCEPT ( 'Table', 'Table'[ActivityID], 'Table'[Resource] )
        
            )
        
        RETURN
        
            'Table'[Budget_overall] / num

         

         

        The result looks like this:

         

         

        Here is the pbix.

         

        Best Regards,

        Caiyun Zheng

         

    • spuff55's avatar
      spuff55
      Frequent Visitor

      HI amitchandak 

      Thanks for the examples, it's a great post but not sure if it solves the problem exactly.