Forum Discussion
Create week number
- 6 years ago
Hello ezequiel
Give this a try.
Column = DATEDIFF ( DATE ( 2019 , 7 , 28 ), 'YourTable'[Date] , WEEK ) +1
The +1 is on the end so the first 7 days don't come back as 0
Hello ezequiel
Give this a try.
Column = DATEDIFF ( DATE ( 2019 , 7 , 28 ), 'YourTable'[Date] , WEEK ) +1
The +1 is on the end so the first 7 days don't come back as 0
Hi jdbuchanan71 . Thanks for your reply.
I tried with
WeekNum = DATEDIFF (DATE(2019,7,28),Tracker[Start of Week],WEEK) +1
I forgot to mention that the table contains this structure:
Subject Hours Start of Week
A 2 7/29/2019
B 3 7/29/2019
A 2 7/29/2019
B 3 8/5/2019
A 3 8/5/2019
The intention is getting something like:
Subject Hours Start of Week Weeknum
A 2 7/29/2019 1
B 3 7/29/2019 1
A 2 7/29/2019 1
B 3 8/5/2019 2
A 3 8/5/2019 2
The suggestion you sent me is giving me an error indicating that "A single value for the column 'Start of Week' in table 'Tracker' cannot be determined"
Thanks
Ezequiel
- jdbuchanan716 years agoSuper User
You would have to add this as a calculated column in your table, not a measure.