Hello,

Based on the following values

 

I have following colum in my task list

Priority

Factor

Max Score

Actual Score

Where should we be?

 

Based on these column I created chart in excel  attached.

 

 

Budget (Where should we be%) 35%
Remaining 65% Where we are? 33%
pointer 0.005
end 1.66
Max 100%
Budget 200%

I need to create same in Power BI. I need to add all the values in Priority
Factor
Max Score
Actual Score
Where should we be? and get the %

 

  • kundan76

     

    You can create some measures as below to get the percent results. For example, we have a table like below.

     

    We need to change the format of these measures to “Percentage”.

    Percent_Where we should be = SUM( Sheet1[Where we should be] ) / SUM( Sheet1[Max Score] )
    Percent_Where we are = SUM( Sheet1[Where we are] ) / SUM( Sheet1[Max Score] )
    Percent_Max = SUM( Sheet1[Max Score] ) / SUM( Sheet1[Max Score] )

    I’ve also uploaded my .pbix file here for reference.

     

    Best Regards,

    Herbert

4 Replies

  • v-haibl-msft's avatar
    v-haibl-msft
    Microsoft Employee

    kundan76

     

    I’m not quite clear about following items you mentioned. According to your chart in excel, I think you can try with the Gauge visual.

     

    pointer 0.005

    end 1.66

    Max 100%

    Budget 200%

     

     

    Best Regards,

    Herbert

    • kundan76's avatar
      kundan76
      Regular Visitor

      Hello Herbert,

      Here are my calculation

      Where we should be =  In Percent (Sum of Where we should be /Sum of Max Score )

      Remining = 100% - Where we should be

      Where we are = In Percent (Sum of Where we are/Sum of Max score

       

      Can you please guide me to create guage . What should I use in value like sum or average or maximum and where

       

      Thanks for your help

       

      • v-haibl-msft's avatar
        v-haibl-msft
        Microsoft Employee

        kundan76

         

        You can create some measures as below to get the percent results. For example, we have a table like below.

         

        We need to change the format of these measures to “Percentage”.

        Percent_Where we should be = SUM( Sheet1[Where we should be] ) / SUM( Sheet1[Max Score] )
        Percent_Where we are = SUM( Sheet1[Where we are] ) / SUM( Sheet1[Max Score] )
        Percent_Max = SUM( Sheet1[Max Score] ) / SUM( Sheet1[Max Score] )