For this requiremnt, you can create two calculated table to achieve it.
Table2 = SUMMARIZE(Table1,Table1[Part Number],Table1[Order Number],"TotalRunTime",CALCULATE(SUM(Table1[Run Time]),ALLEXCEPT(Table1,Table1[Part Number],Table1[Order Number])),"Output Quantity",CALCULATE(MAX(Table1[Output Quantity]),ALLEXCEPT(Table1,Table1[Part Number],Table1[Order Number])))Table3 = SUMMARIZE(Table2,Table2[Part Number],"TotalRunTime",CALCULATE(SUM(Table2[TotalRunTime]),ALLEXCEPT(Table2,Table2[Part Number])),"TotalOutputQuantity",CALCULATE(SUM(Table2[Output Quantity]),ALLEXCEPT(Table2,Table2[Part Number])))
Average = Table3[TotalRunTime]/Table3[TotalOutputQuantity]Regards,
Chalrie Liao
Hi, Put in a table visual Order Number and RunTime
After That Click in Run Time and Select Sum.
Thanks Vvelarde, that certianly gets what I'm needing but not what I want. This is my mistake for not fully explaining my goal.
I need to know what the total Run Time is for every Order Number so that I can then average that run time against a Quantity column which is also in the data to give me an average Run Time per Part Number. Below is a more representative set of data to help explain what I'm trying to do. (Note: for Output Quantity I will pull the MAX value as these are not summed. Example: 10001 has a total output quantity of 15, not 60).
| Order Number | Part Number | Run Time | Output Quantity |
| 10001 | Widget A | 5 | 15 |
| 10001 | Widget A | 60 | 15 |
| 10001 | Widget A | 10 | 15 |
| 10001 | Widget A | 80 | 15 |
| 10002 | Widget B | 4 | 10 |
| 10002 | Widget B | 10 | 10 |
| 10002 | Widget B | 5 | 10 |
| 10003 | Widget A | 90 | 5 |
| 10004 | Widget B | 50 | 20 |
| 10004 | Widget B | 75 | 20 |
| 10004 | Widget B | 60 | 20 |
| 10004 | Widget B | 10 | 20 |
This data will be summarized and presented as part of several visualizations.
| Part Number | Average Run Time |
| Widget A | 12.25 |
| Widget B | 7.13 |
- v-caliao-msft9 years ago
Microsoft Employee
For this requiremnt, you can create two calculated table to achieve it.
Table2 = SUMMARIZE(Table1,Table1[Part Number],Table1[Order Number],"TotalRunTime",CALCULATE(SUM(Table1[Run Time]),ALLEXCEPT(Table1,Table1[Part Number],Table1[Order Number])),"Output Quantity",CALCULATE(MAX(Table1[Output Quantity]),ALLEXCEPT(Table1,Table1[Part Number],Table1[Order Number])))Table3 = SUMMARIZE(Table2,Table2[Part Number],"TotalRunTime",CALCULATE(SUM(Table2[TotalRunTime]),ALLEXCEPT(Table2,Table2[Part Number])),"TotalOutputQuantity",CALCULATE(SUM(Table2[Output Quantity]),ALLEXCEPT(Table2,Table2[Part Number])))
Average = Table3[TotalRunTime]/Table3[TotalOutputQuantity]Regards,
Chalrie Liao