Frequent Visitor

Create Rundown/Burndown Curve

Hi all,

 

My company has recently adopted Power BI as the progress reporting tool of choice and I'm in process of learning how to use it.

 

The below screen shot shows a rundown/burndown curve I've developed in Excel. I need to re-create something similar in Power BI.  The 'Progress Dashboard' link has a power BI file that I've uploaded the same two spreadsheets required to make the rundown curve as seen in the screenshot.

 

Progress Dashboard

 

rundown screenshot.png

The common column between the two tables is titled "sub-system".

The "MC Finish Date" table only has two column of importance (Sub-system and MC Finish Date).

The "Checksheets" table also only has two columns of importance (Sub-System and Discipline (Summary)).

 

I only started reviewing Power BI turorials a few days ago so would appreciate any assistance people can offer.

 

Thanks in advance.

1 ACCEPTED SOLUTION

Thanks for replying Jimmy.

 

In order for me to make it work in Excel I had to lookup the MC Finish Date for each sub-system from the MC Finish Date table and count how many dates fell in a particular week. Once calculated, I'd tabulate the totals and generate the rundown curve accordingly. The below link shows how I do it in excel:

 

https://1drv.ms/f/s!Ap_6-ICMV1K6ed9-ueXp0nMNL-0

 

This is the sequence of activities required to generate in excel:

 

1. Import MC finish date to checksheet tab (column AN)

2. Count total weekly completed sub-systems (CalcSheet tab - columns K3:EU3)

3. Generate rundown figures for chart (CalcSheet tab - columns K4:EU4)

4. Create chart with above figures (Dashboard tab charts)

 

Hope this helps shine a bit more light on what I need to develop.

View solution in original post

3 REPLIES 3
v-yuta-msft
Community Support
Community Support

Hi jeversf,

 

Not very clear about which columns can be used to create the chart, to be general, the result will like below:

11.PNG 

 

Regards,

Jimmy Tao

Thanks for replying Jimmy.

 

In order for me to make it work in Excel I had to lookup the MC Finish Date for each sub-system from the MC Finish Date table and count how many dates fell in a particular week. Once calculated, I'd tabulate the totals and generate the rundown curve accordingly. The below link shows how I do it in excel:

 

https://1drv.ms/f/s!Ap_6-ICMV1K6ed9-ueXp0nMNL-0

 

This is the sequence of activities required to generate in excel:

 

1. Import MC finish date to checksheet tab (column AN)

2. Count total weekly completed sub-systems (CalcSheet tab - columns K3:EU3)

3. Generate rundown figures for chart (CalcSheet tab - columns K4:EU4)

4. Create chart with above figures (Dashboard tab charts)

 

Hope this helps shine a bit more light on what I need to develop.

Above link now contains solution.

Helpful resources

Announcements
FabCon and SQLCon Barcelona 2026

FabCon & SQLCon – Barcelona 2026

Join us in Barcelona for FabCon and SQLCon, the Fabric, Power BI, SQL, and AI community event. Save €200 with code FABCMTY200.

60 days of Data Days Carousel

Data Days 2026

Join Data Days 2026: 60 days of free live/on-demand sessions, challenges, study groups, and certification opportunities.

Power BI DataViz World Championships carousel

Power BI DataViz World Championships - June 2026

A new Power BI DataViz World Championship is coming this June! Don't miss out on submitting your entry.

Top Solution Authors