Hi

 

I hope someone can help

 

I am attempting to create a report in BI which shows the change of a project though its life. To do this I will need to access all of the previous baselines and their respective variences. Is this possible?

 

I know that the current duration varience is based on what ever the active baseline is set to in MSP so i assume i will need calculated columns to work aout the varience between e.g. baseline 1, baseline 2 etc... However I am not sure how to show all the baselines, rather than just the active one

 

Thanks for your help

 

Matt

1 ACCEPTED SOLUTION
Matt22365
Resolver III
Resolver III

I found a way round the issue, I created new calculated fields in the source data creating new variance columns for each baseline. This then translates down into BI

 

Thanks

 

Matt

View solution in original post

1 REPLY 1
Matt22365
Resolver III
Resolver III

I found a way round the issue, I created new calculated fields in the source data creating new variance columns for each baseline. This then translates down into BI

 

Thanks

 

Matt

Helpful resources

Announcements
August Power BI Update Carousel

Power BI Monthly Update - August 2025

Check out the August 2025 Power BI update to learn about new features.

August 2025 community update carousel

Fabric Community Update - August 2025

Find out what's new and trending in the Fabric community.

Top Solution Authors