Connect to multiple baselines in MS Project
Hi I hope someone can help I am attempting to create a report in BI which shows the change of a project though its life. To do this I will need to access all of the previous baselines and the...
- 8 years ago
I found a way round the issue, I created new calculated fields in the source data creating new variance columns for each baseline. This then translates down into BI
Thanks
Matt
Matt22365
8 years agoResolver III
I found a way round the issue, I created new calculated fields in the source data creating new variance columns for each baseline. This then translates down into BI