Hi

I have a matrix showing % complete of various aspects of projects.  I would like for example to show everything that is 80% - 95% as yellow, 96-100% as green, and everything over 100% as red.  I have had an attempt with the advanced controls on the background colour but cannot get it to work as I need.

 

All the values are measures using CALCULATE and formatted as %

 

Any help much appreciated

 

matrix.jpg

 

1 ACCEPTED SOLUTION
rajulshah
Resident Rockstar
Resident Rockstar

Hello @sanderson82,

 

Go to Advanced Controls for the field plotted in matrix, then select Rules and select your field that is plotted.
Then give the rules as in the image below. Please make sure you select 'Number' for rules.
cf%.png

Hope this helps.

View solution in original post

1 REPLY 1
rajulshah
Resident Rockstar
Resident Rockstar

Hello @sanderson82,

 

Go to Advanced Controls for the field plotted in matrix, then select Rules and select your field that is plotted.
Then give the rules as in the image below. Please make sure you select 'Number' for rules.
cf%.png

Hope this helps.

Helpful resources

Announcements
FabCon and SQLCon Barcelona 2026

FabCon & SQLCon – Barcelona 2026

Join us in Barcelona for FabCon and SQLCon, the Fabric, Power BI, SQL, and AI community event. Save €200 with code FABCMTY200.

60 days of Data Days Carousel

Data Days 2026

Join Fabric Data Days 2026: 60 days of free live/on-demand sessions, challenges, study groups, and certification opportunities.

Power BI DataViz World Championships carousel

Power BI DataViz World Championships - June 2026

A new Power BI DataViz World Championship is coming this June! Don't miss out on submitting your entry.