Forum Discussion
Conditional format based on start and end date
- 6 years ago
Hi Anonymous ,
Regarding your questions you can do the following:
More than 1 week
Create a measure:
Number of days = SUMX('Table';DATEDIFF('Table'[Schedule Start date];'Table'[Schedule End date];DAY)) + 1Adjust your previous measure to:
Day of the week calculation = IF ( [Number of days] > 7; 1; IF ( WEEKDAY ( MAX ( 'Table'[Schedule Start Date] ); 1 ) > MAX ( 'Weekdays'[ID] ) || WEEKDAY ( MAX ( 'Table'[Schedule End Date] ); 1 ) < MAX ( 'Weekdays'[ID] ); 0; 1 ) )Assuming you want to have all days ocupied correct?
Making use of a table
Instead of making a measure make one for each of the weekdays and place them on your table then use the same condittional formatting.
Monday = IF ( [Number of days] > 7; 1; IF ( WEEKDAY ( MAX ( 'Table'[Schedule Start Date] ); 1 ) > 2 || WEEKDAY ( MAX ( 'Table'[Schedule End Date] ); 1 ) < 2; 0; 1 ) ) Tuesday = IF ( [Number of days] > 7; 1; IF ( WEEKDAY ( MAX ( 'Table'[Schedule Start Date] ); 1 ) > 3 || WEEKDAY ( MAX ( 'Table'[Schedule End Date] ); 1 ) < 3; 0; 1 ) ) Wednesday = IF ( [Number of days] > 7; 1; IF ( WEEKDAY ( MAX ( 'Table'[Schedule Start Date] ); 1 ) > 4 || WEEKDAY ( MAX ( 'Table'[Schedule End Date] ); 1 ) < 4; 0; 1 ) ) Thursday = IF ( [Number of days] > 7; 1; IF ( WEEKDAY ( MAX ( 'Table'[Schedule Start Date] ); 1 ) > 5 || WEEKDAY ( MAX ( 'Table'[Schedule End Date] ); 1 ) < 5; 0; 1 ) ) Friday = IF ( [Number of days] > 7; 1; IF ( WEEKDAY ( MAX ( 'Table'[Schedule Start Date] ); 1 ) > 6 || WEEKDAY ( MAX ( 'Table'[Schedule End Date] ); 1 ) < 6; 0; 1 ) )Check PBIX file attach with both options.
Regards,
MFelix
Hi Anonymous ,
Create a table with the days of the week (don't include the weekends):
ID Day of the week
| 2 | Monday |
| 3 | Tuesday |
| 4 | Wednesday |
| 5 | Thursday |
| 6 | Friday |
Now add the following measure to your model:
Day of the week calculation =
IF (
WEEKDAY ( MAX ( 'Table'[Schedule Start Date] ); 1 ) > MAX ( 'Week Days'[ID] )
|| WEEKDAY ( MAX ( 'Table'[Schedule End Date] ); 1 ) < MAX ( 'Week Days'[ID] );
0;
1
)
Now construct the following matrix:
- Rows:
- Batch
- Start Date
- End Date
- ....
- Other Columns
- Columns:
- Day of the week (previous create table)
- Values
- Measure [Day of the week calculation]
Now add conditional formatting for 1 (black) and 0 (white) on the background and font color.
Result attach.
Please be aware that looking at your data you do not have value that go more than 2 or 3 days if difference of dates is bigger than 1 week you my need to make some adjustments.
Regards.
MFelix
Hi MFelix ,
Thanks for this great help.
The solution seems very close. I have incorporated the solution in the files below.
As you guessed it right, We do have items that run over a week, so i would need your help to capture this scenario as well.
Is there a way to achieve this result in a calculated column and table view instead of matrix view as it could be convenient??
We would like to view a line item as a seperate row without any grouping, whereas matrix groups rows if i am not wrong.
- MFelix6 years agoSuper User
Hi Anonymous ,
Regarding your questions you can do the following:
More than 1 week
Create a measure:
Number of days = SUMX('Table';DATEDIFF('Table'[Schedule Start date];'Table'[Schedule End date];DAY)) + 1Adjust your previous measure to:
Day of the week calculation = IF ( [Number of days] > 7; 1; IF ( WEEKDAY ( MAX ( 'Table'[Schedule Start Date] ); 1 ) > MAX ( 'Weekdays'[ID] ) || WEEKDAY ( MAX ( 'Table'[Schedule End Date] ); 1 ) < MAX ( 'Weekdays'[ID] ); 0; 1 ) )Assuming you want to have all days ocupied correct?
Making use of a table
Instead of making a measure make one for each of the weekdays and place them on your table then use the same condittional formatting.
Monday = IF ( [Number of days] > 7; 1; IF ( WEEKDAY ( MAX ( 'Table'[Schedule Start Date] ); 1 ) > 2 || WEEKDAY ( MAX ( 'Table'[Schedule End Date] ); 1 ) < 2; 0; 1 ) ) Tuesday = IF ( [Number of days] > 7; 1; IF ( WEEKDAY ( MAX ( 'Table'[Schedule Start Date] ); 1 ) > 3 || WEEKDAY ( MAX ( 'Table'[Schedule End Date] ); 1 ) < 3; 0; 1 ) ) Wednesday = IF ( [Number of days] > 7; 1; IF ( WEEKDAY ( MAX ( 'Table'[Schedule Start Date] ); 1 ) > 4 || WEEKDAY ( MAX ( 'Table'[Schedule End Date] ); 1 ) < 4; 0; 1 ) ) Thursday = IF ( [Number of days] > 7; 1; IF ( WEEKDAY ( MAX ( 'Table'[Schedule Start Date] ); 1 ) > 5 || WEEKDAY ( MAX ( 'Table'[Schedule End Date] ); 1 ) < 5; 0; 1 ) ) Friday = IF ( [Number of days] > 7; 1; IF ( WEEKDAY ( MAX ( 'Table'[Schedule Start Date] ); 1 ) > 6 || WEEKDAY ( MAX ( 'Table'[Schedule End Date] ); 1 ) < 6; 0; 1 ) )Check PBIX file attach with both options.
Regards,
MFelix