Forum Discussion
Computing rollup weighted sum
- 7 years ago
So based on your new requirement to apply the weightings differently at different levels you might be able to do something like the following which just dynamically changes the factor inside the SUMX based on which columns are filtered
SUMX( table1, IF(ISFILTERED( table1[Project]), 1, -- at the project level multiply by 1
IF( ISFILTERED(Program], [Project Weightage], -- at the program level apply the project weight
[Program Weightage] * [Project Weightage]) -- at the total level apply program and project weighting
* [Progress])
The computation of the Progess (%) should be dynamic based on which level is selected.
For eg:-
When selected Project A, Progress (%) = 4.8%
When selected Program 1, Progress (%)= = 0.94%
When selected Program 2, Progress (%) = 2.4%
When selected Overall Progress (Program 1 and Program 2), the Progresss (%) = 1.96%
I don't think in this case, SUMX( <table name>, [Program Weightage] * [Project Weightage] * [Progress]) works.
So based on your new requirement to apply the weightings differently at different levels you might be able to do something like the following which just dynamically changes the factor inside the SUMX based on which columns are filtered
SUMX( table1, IF(ISFILTERED( table1[Project]), 1, -- at the project level multiply by 1
IF( ISFILTERED(Program], [Project Weightage], -- at the program level apply the project weight
[Program Weightage] * [Project Weightage]) -- at the total level apply program and project weighting
* [Progress])
- jav2267 years agoFrequent Visitor
Hi,
I hit another roadblock, hope you can assist again.
Your DAX works perfectly fine when I display the records in a table.
When I display a chart showing the overall All Programs progress, and start to slice to only Project A and Project B, it sums up the Progress of Project A and Project B which is not correct. Because I'm at overall All Programs level, the expectation is to sum up the progress of Project A and Project B with consideration of the Project and Program weightage.
- d_gosbell7 years agoSuper User
It should not matter if the data is visualized in a table or a chart.
But I don't really understand what your issue is - I can't understand how you can be both at the total level and slicing by a project. Can you maybe share a screenshot or something?
- jav2267 years agoFrequent Visitor
In Pic01 below, when I'm not slicing any Project, the overall progress of 0.82% at the bar chart is correct.
Pic01
But at Pic02 below, when I slice to Project A and Project E, the Overall Progress in bar chart becomes 14.31%. The expected progress should be 0.64% [ Project A (8.14% * 8.80% * 36%) + Project E (6.17% * 9.60% * 64%)].
Pic02
My DAX script as following:-Cumm Planned (%) =SUMX(All_DATA, IF(ISFILTERED( 'ALL_DATA'[L4 - Discipline]), [Planned (%)],IF( ISFILTERED('ALL_DATA'[L3 - Phase]), [L4 Weightage (%)], IF( ISFILTERED('ALL_DATA'[L2 - Package]), [L3 Weightage (%)] * [L4 Weightage (%)],[L2 EPCC Weightage (%)] * [L3 Weightage (%)] *[L4 Weightage (%)])) * [Planned (%)]))