Computing Resource Utilization Per Day, Week and Month
- 8 years ago
Wow that fixed it! I changed the relationship to both and changed the %Utilization to use:
%Utilization = DIVIDE([#Hours Spent],SUM('Developer Date Table'[Hours Required]),0)
You're amazing parry2k!
Here's the result that makes more sense. :)
- 8 years ago
hahaha, same here, Bud. Thanks a lot! You're a great help..:smileyhappy:
Here's the link to the file that I'm working on. Hope this helps.
https://drive.google.com/file/d/1v84kSThkFZHJKbIaDG2vOpCK-b9XyKvd/view?usp=sharing
ok, no worries, which tab should I focus on?
- polaris30288 years agoHelper III
The Utilization tab please. :)
- parry2k8 years agoSuper User
what output your are expecting? you already have stuff on there, so not sure what is not working?
- polaris30288 years agoHelper III
per resource it looks good, but the sum utilization for the entire day is not correct. The GrandTotal for #Hours Required for the day is not 7.5, but should be #Resource*7.5