I am trying to create a resource capacity matrix and need help with creating a measure that would aggregate the capacity of a resource by each month based start date & end date of the projects assign...
  • v-robertq-msft's avatar
    5 years ago

    Hi, Prath 

    According to your description, I can roughly understand your requirement, I think you can try my measure to achieve this:

    First, you should delete the relationship between the calendar table with the main table to avoid errors.

     

    Then create a measure like this:

    Capacity1 =
    
    var _value=
    
    CALCULATE(SUM(Data[Capacity]),FILTER('Data',[Start]<=MIN('Calendar_Date'[Date])&&[End]>=MAX('Calendar_Date'[Date])))
    
    return
    
    IF(_value=BLANK(),0,_value)

    Then create a matrix and place it and apply a filter like this:

     

    And you can get what you want.

    You can download my test pbix file below