Capping a cumulative total
- echall936 years agoFrequent Visitor
Hi Jimmy Tao,
Thanks for getting back to me! This is a sample of the data I'm using for one of the projects:
Date Project Working days Cost of day (optimum) Start of month Revenue 30 September 2019 Wilts006 1 £1,230.02 01 September 2019 51428.91 19 September 2019 Wilts006 1 £1,230.02 01 September 2019 51428.91 18 September 2019 Wilts006 1 £1,230.02 01 September 2019 51428.91 04 September 2019 Wilts006 1 £1,230.02 01 September 2019 51428.91 03 September 2019 Wilts006 1 £1,230.02 01 September 2019 51428.91 02 September 2019 Wilts006 1 £1,230.02 01 September 2019 51428.91 28 October 2019 Wilts006 1 £1,230.02 01 October 2019 51428.91 24 October 2019 Wilts006 1 £1,230.02 01 October 2019 51428.91 23 October 2019 Wilts006 1 £1,230.02 01 October 2019 51428.91 16 October 2019 Wilts006 1 £1,230.02 01 October 2019 51428.91 15 October 2019 Wilts006 1 £1,230.02 01 October 2019 51428.91 14 October 2019 Wilts006 1 £1,230.02 01 October 2019 51428.91 09 October 2019 Wilts006 1 £1,230.02 01 October 2019 51428.91 02 October 2019 Wilts006 1 £1,230.02 01 October 2019 51428.91 01 October 2019 Wilts006 1 £1,230.02 01 October 2019 51428.91 30 September 2019 Wilts006 1 £825.50 01 September 2019 51428.91 30 September 2019 Wilts006 1 £825.50 01 September 2019 51428.91 27 September 2019 Wilts006 1 £825.50 01 September 2019 51428.91 27 September 2019 Wilts006 1 £825.50 01 September 2019 51428.91 26 September 2019 Wilts006 1 £825.50 01 September 2019 51428.91 26 September 2019 Wilts006 1 £825.50 01 September 2019 51428.91 25 September 2019 Wilts006 1 £825.50 01 September 2019 51428.91 25 September 2019 Wilts006 1 £825.50 01 September 2019 51428.91 24 September 2019 Wilts006 1 £825.50 01 September 2019 51428.91 23 September 2019 Wilts006 1 £825.50 01 September 2019 51428.91 20 September 2019 Wilts006 1 £825.50 01 September 2019 51428.91 19 September 2019 Wilts006 1 £825.50 01 September 2019 51428.91 19 September 2019 Wilts006 1 £825.50 01 September 2019 51428.91 18 September 2019 Wilts006 1 £825.50 01 September 2019 51428.91 17 September 2019 Wilts006 1 £825.50 01 September 2019 51428.91 16 September 2019 Wilts006 1 £825.50 01 September 2019 51428.91 13 September 2019 Wilts006 1 £825.50 01 September 2019 51428.91 13 September 2019 Wilts006 1 £825.50 01 September 2019 51428.91 12 September 2019 Wilts006 1 £825.50 01 September 2019 51428.91 11 September 2019 Wilts006 1 £825.50 01 September 2019 51428.91 10 September 2019 Wilts006 1 £825.50 01 September 2019 51428.91 09 September 2019 Wilts006 1 £825.50 01 September 2019 51428.91 06 September 2019 Wilts006 1 £825.50 01 September 2019 51428.91 05 September 2019 Wilts006 1 £825.50 01 September 2019 51428.91 04 September 2019 Wilts006 1 £825.50 01 September 2019 51428.91 03 September 2019 Wilts006 1 £825.50 01 September 2019 51428.91 02 September 2019 Wilts006 1 £825.50 01 September 2019 51428.91 28 October 2019 Wilts006 1 £825.50 01 October 2019 51428.91 21 October 2019 Wilts006 1 £825.50 01 October 2019 51428.91 18 October 2019 Wilts006 1 £825.50 01 October 2019 51428.91 17 October 2019 Wilts006 1 £825.50 01 October 2019 51428.91 16 October 2019 Wilts006 1 £825.50 01 October 2019 51428.91 16 October 2019 Wilts006 1 £825.50 01 October 2019 51428.91 15 October 2019 Wilts006 1 £825.50 01 October 2019 51428.91 15 October 2019 Wilts006 1 £825.50 01 October 2019 51428.91 14 October 2019 Wilts006 1 £825.50 01 October 2019 51428.91 14 October 2019 Wilts006 1 £825.50 01 October 2019 51428.91 11 October 2019 Wilts006 1 £825.50 01 October 2019 51428.91 10 October 2019 Wilts006 1 £825.50 01 October 2019 51428.91 10 October 2019 Wilts006 1 £825.50 01 October 2019 51428.91 09 October 2019 Wilts006 1 £825.50 01 October 2019 51428.91 08 October 2019 Wilts006 1 £825.50 01 October 2019 51428.91 07 October 2019 Wilts006 1 £825.50 01 October 2019 51428.91 04 October 2019 Wilts006 1 £825.50 01 October 2019 51428.91 03 October 2019 Wilts006 1 £825.50 01 October 2019 51428.91 01 October 2019 Wilts006 1 £825.50 01 October 2019 51428.91 23 August 2019 Wilts006 1 £1,058.41 01 August 2019 51428.91 23 September 2019 Wilts006 1 £1,058.41 01 September 2019 51428.91 28 August 2019 Wilts006 1 £1,058.41 01 August 2019 51428.91 27 August 2019 Wilts006 1 £1,058.41 01 August 2019 51428.91 22 August 2019 Wilts006 1 £1,058.41 01 August 2019 51428.91 26 August 2019 Wilts006 0 £0.00 01 August 2019 51428.91 24 September 2019 Wilts006 0.5 £412.75 01 September 2019 51428.91 12 September 2019 Wilts006 0.5 £412.75 01 September 2019 51428.91 29 October 2019 Wilts006 0.5 £412.75 01 October 2019 51428.91 02 October 2019 Wilts006 0.5 £412.75 01 October 2019 51428.91 01 October 2019 Wilts006 0.5 £412.75 01 October 2019 51428.91 In the Matrix Visualisation I've then got two measures: Cumulative month and Realised revenue 1
Cumulative month = CALCULATE(
SUM('Timesheets'[Cost of day (optimum)]),
FILTER(
ALLSELECTED('Timesheets'[Start of month].[Date]),
ISONORAFTER('Timesheets'[Start of month].[Date],MAX('Timesheets'[Start of month].[Date]),DESC)
))Realised revenue1 = IF('Timesheets'[Cumulative month]<MAX('Timesheets'[Revenue]),
SUM('Timesheets'[Cost of day (optimum)]),
IF(CALCULATE('Timesheets'[Cumulative month],PREVIOUSMONTH('Timesheets'[Start of month].[Date]))<MAX('Timesheets'[Revenue]),
'Timesheets'[Cumulative month]-MAX('Timesheets'[Revenue]),
0))The expected outcome is:Month Monthly cost of days Cumulative month Realised revenue Jul £ - £ - Aug £ 4,233.64 £ 4,233.64 £ 4,233.64 Sep £ 31,552.53 £ 35,786.17 £ 31,552.53 Oct £ 24,302.87 £ 60,089.04 £ 15,642.74 Thank you again v-yuta-msft!
- v-yuta-msft6 years ago
Community Support
echall93 ,
I got the same result as your first screenshot, could you please clarify the to achieve the aggregation values in Oct?
Community Support Team _ Jimmy Tao
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
- echall936 years agoFrequent Visitor
The value should be £15,642.74 (which is the revenue for the project, minus the realised revenue so far, i.e. £4,233.64 + £31,552.53). I'm not sure how to get Power BI to take the revenue for the project minus the cumulative revenue last month, which is what would allow me to do the above?