Calculating future dates from a project start date

Hi all,   Im looking to do a calculation that will provide me with future 'no later than' dates for a survey.    I have a project start date (01.01.20) and project end date (31.12.20) and want a ...
  • amitchandak's avatar
    6 years ago

    eilidh3 , Both as new columns

    mid date = [start_date]+ quotient(datediff([start_date],[end_date],day),2)
    one month after date = date(year([end_date]),month([end_date])+1,day([end_date]))