Calculate difference between two dates power query

How do I calculate the difference between two dates in Power Query M code (not DAX)?  I'm looking for the number of days.

1 ACCEPTED SOLUTION
LivioLanzo
Solution Sage
Solution Sage

Hi @jshutters

 

you need to use the duration functions: https://docs.microsoft.com/en-us/powerquery-m/duration-days

 

=each Duration.Days([Date1] - [Date2])

 

 

 


 


Did I answer your question correctly? Mark my answer as a solution!


Proud to be a Datanaut!  

View solution in original post

10 REPLIES 10
Rickmaurinus
Helper V
Helper V

jshutters,

 

Good question. Your question depends on the following: 

 

1. Do you need the number of days between 2 dates?


Use Duration.Days ( [EndDate] - [StartDate] ) +1
2. Do you need the number of weekdays between 2 dates? 


 Generate a list of dates between start and enddate, and remove the weekends. Count the number of days left in your list.

 

3. Do you need working days between 2 dates? 

 

Generate a list of dates between start and enddate, remove weekends and holidays. Then count the number of days left in your list.  

 

For 2 and 3 I'll just drop this blog here so you can read the details. It's a bit more complex but replicates the DATEDIFF function for the M language: 

 

https://gorilla.bi/power-query/working-days-between-dates/

 

Cheers!

Rick

 

--------------------------------------------------

 

@ me in replies or I'll lose your thread

 

Master Power Query M? -> https://powerquery.how

Read in-depth articles? -> BI Gorilla

Youtube Channel: BI Gorilla

 

If this post helps, then please consider accepting it as the solution to help other members find it more quickly.

J2008F
New Member

Hello 

 

How do I calculate the years between 2 dates on power query M coding?

 Date formate is e.g. 2022-12-10

J2008F, to calculate the years between 2 dates, you can use the Date.Year function in M coding.  For example, Date.Year(<insert name of column2>) - Date.Year(<insert name of column1>)

raymondwkmok
New Member

A further queston on Duration.Days, the formula Duration.Days([Date1] - [Date2]) did not cater both date inclusive situation. Is there any way to modify the formula for both date inclusve situation? 

Example, The Duration.Days formula gives 6 for days between 2022/02/22 and 2022/02/28, but it should be 7 if both date inclusive.

Just add one day to the first date: Duration.Days(Date.AddDays([Date1],1) - [Date2])

Or just add one to the result: Duration.Days([Date1] - [Date2])+1

rfratto
Advocate I
Advocate I

One note: I kept receiving errors on the [Date1] - [Date2] until I explicitly converted my date values to a date using Date.From(): e.g. (for an aging calculation)  

 

= Duration.Days(Date.From(DateTime.LocalNow()) - Date.From([Due_Date]))

Hello is it possible to calculate number of days using date that I specify. I need to calculate number of day between August 31, 2021 and some Due date I have in data. When I use this formula Duration.Days(Date.From(2021-08-31) - Date.From([DEB_DAT])), it returns strange result.

 

Thanks for help

jbocachica
Resolver II
Resolver II

Hi, you can find the solution in this post.

 

http://blog.iwco.co/2018/12/07/numero-de-dias-entre-dos-fechas-power-query-m/

 

Regards

John Bocachica
Senior BI Consultant
Information Workers
http://www.iwco.co
LivioLanzo
Solution Sage
Solution Sage

Hi @jshutters

 

you need to use the duration functions: https://docs.microsoft.com/en-us/powerquery-m/duration-days

 

=each Duration.Days([Date1] - [Date2])

 

 

 


 


Did I answer your question correctly? Mark my answer as a solution!


Proud to be a Datanaut!  

In similar cases is better to use DAX or PowerQuery to this calculations?

Can anyone write advantages and disadventages this two ways of solving similar cases?

Helpful resources

Announcements
Europe Fabric Conference

Europe’s largest Microsoft Fabric Community Conference

Join the community in Stockholm for expert Microsoft Fabric learning including a very exciting keynote from Arun Ulag, Corporate Vice President, Azure Data.

Power BI Carousel June 2024

Power BI Monthly Update - June 2024

Check out the June 2024 Power BI update to learn about new features.

PBI_Carousel_NL_June

Fabric Community Update - June 2024

Get the latest Fabric updates from Build 2024, key Skills Challenge voucher deadlines, top blogs, forum posts, and product ideas.

Top Solution Authors