Forum Discussion
Calculate Date and Time difference considering the weekends and workhours
- 10 years ago
The only possibility I can think of is that there is something wrong with the Calendar'[WorkDay] formula. Could you please check this column formula is like below? The data type of this column should be “True/False”.
If it is actually same as mine, could you please upload your .pbix file to OneDrive and share it with me? In that case I can take a look at your .pbix file and try to solve the problem.
Best Regards,
Herbert
- 9 years ago
How about the result if we update the “FirstDaySecDiff” measure as below?
FirstDaySecDiff = IF ( Table1[FirstDayEndTime] >= Table1[DateTimeFrom] && Table1[FirstDayEndTime] <= Table1[DateTimeTo], DATEDIFF ( Table1[DateTimeFrom], Table1[FirstDayEndTime], SECOND ), IF ( Table1[FirstDayEndTime] >= Table1[DateTimeFrom] && Table1[FirstDayEndTime] > Table1[DateTimeTo], DATEDIFF ( Table1[DateTimeFrom], Table1[DateTimeTo], SECOND ), 0 ) )Best Regards,
Herbert
itshudak can you put together a reproducible example? Check this out for pointers
Easiest way would be to put together a CSV with 2 columns (start and end time) and 5-10 rows, made up from your problem rows. Import this into Power BI and make sure you still get the error
I'll then check it out and see what I can do
Nevermind, consider this egg on my face. It was actually an issue with the stop time being before the start time and I was just getting mixed up. Thank you for your help with this, I appreciate it.