Building a Gantt Chart focused on Resources

Hello! I am working on building a gantt chart that is more focused on Resources than Projects. That may sound strange but here is a picture of what I am looking for:

mgwarren94_0-1648182167634.png

 

The idea is, I don't care about tasks and how many people have. I am more focused on when can we get the next project scheduled. I would like to be able to have my resources on the left side and then have all the projects they are a part of the view in the Gantt style. 

 

The problem that I am running into is when I pull my data into PowerBI my 'resource' column has multiple names so I can't combine the projects that just 'Adam' is a part of. 

 

What I have done:

  • I am using the Microsoft Gantt Template
  • I have separated out the resources column by the comma and created a new column per resource
    • The problem with this, I can't seem to add 10+ resource columns to one data field in powerbi... (ignore the 'task' title that is how I am able to get the resources on the right hand side)
    • mgwarren94_1-1648182860048.png

       

Questions:

  • What is the best way to separate the resource column?
  • Will separating that column out work for what I am looking to do? 

 

1 ACCEPTED SOLUTION
Icey
Community Support
Community Support

Hi @Anonymous ,

 

Duplicate values won't show in a slicer visual. Please check for spaces, etc. that cause the two to not be exactly the same.

Icey_0-1648519113485.png

 

 

Best Regards,

Icey

 

If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

View solution in original post

4 REPLIES 4
Anonymous
Not applicable

Unfortunately, that does not solve my problem. 

 

See the screenshot below. When I select both Adams, I get all of the projects that he is a resource on. But if I select one of the names, I get different information... see screen shot #2

mgwarren94_0-1648470369008.png

 

 

Screenshot #2

mgwarren94_1-1648470429677.png

 

Icey
Community Support
Community Support

Hi @Anonymous ,

 

Duplicate values won't show in a slicer visual. Please check for spaces, etc. that cause the two to not be exactly the same.

Icey_0-1648519113485.png

 

 

Best Regards,

Icey

 

If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

Anonymous
Not applicable

Update. I am almost there. I ended up splitting the 'resources' column into ROWs and not COLUMNs. This 'worked' and is working for what I need it to do. It is not pretty. 

 

New problem. Because of this, I know how duplicated ID numbers. I added a slicer that pulls the resources column but I see multiple of the same resource name when I go to select the resource.  Different information shows in the gantt chart depending on which First Last name I select. 

 

It looks like this:

  • Resources
    • Bob Smith
    • Johnny Apple
    • Zeke Iron
    • Bob Smith

Question:

  • How do I remove those duplicates but still get the information that is needed in the Gantt Chart?
Icey
Community Support
Community Support

Hi @Anonymous ,

 

Please turn on "Group Tasks" option.

Icey_0-1648458926675.png

gantt.gif

 

 

 

Best Regards,

Icey

 

If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

Helpful resources

Announcements
Fabric Data Days Carousel

Fabric Data Days

Advance your Data & AI career with 50 days of live learning, contests, hands-on challenges, study groups & certifications and more!

October Power BI Update Carousel

Power BI Monthly Update - October 2025

Check out the October 2025 Power BI update to learn about new features.

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.

Top Solution Authors