Forum Discussion
Adding a Projection to Historical Data
- 6 years ago
Your forecast seems to be pretty low. Do you want us to correct forecast calculation?
What I'd like is for the Forecast be the last month with actual QOH PLUS the forecast for each month (based on demand and incoming POs). I could just enter the previous month's amount and sum that with the demand and POs, but I'd like to use time intelligence so I don't have to go into the file to change it. This way it would look like the Historical QOH w/ the red line in my first post.
Here is my attempt that doesn't do what I want it to do.
QOH + Forecast =
CALCULATE('zz - Practice QOH'[Historical QOH (Measure)],LASTDATE('zz - Practice QOH'[Date]) ) + [Forecast]Here is the code for the below chart. What I'd like is to have a measure that produces the line from Historical QOH for all past dates, and Last Month's QOH + Forecast for the future dates.
QOH + Forecast =
[Forecast] + 1550- amitchandak6 years agoSuper User
I got a measure like this. You need to adjust the other than _last, That I made constant now.
Final POH = var _max = maxx(filter(all('zz - Practice QOH'),'zz - Practice QOH'[Historical QOH]>0),'zz - Practice QOH'[Date]) Var _last =sumx(SUMMARIZE('zz - Practice QOH',"_max1",maxx(filter(all('zz - Practice QOH'),'zz - Practice QOH'[Date]>=_max),'zz - Practice QOH'[Historical QOH])),[_max1]) return _last+SUM('zz - Practice QOH'[Demand])+SUM('zz - Practice QOH'[POs Landing])Please find the attached file
- Anonymous6 years agoNot applicable
We are closer! Thanks!
Now, can we get the "Final POH" to be the Historical QOH for all past dates, and your projections for future dates?
- amitchandak6 years agoSuper User
Anonymous
I think that is what it is on page 3. Please check.