Forum Discussion
Adding X Business\Working Days to another date.
- 2 years ago
StuartSmith This depends on your logic. The way this is written, January 8th is working day +0, January 9th is working day +1 (from the Start Date). It seems you want to count the start date as the first working day. In that case, remove the +1 from the CALENDAR function so CALENDAR( [Start Date], [Start Date] + __Days)
Thanks, I have it working, of sorts, but as an example, the start date is Mondays 8th Jan and 35 Business days would be Fri 23rd Feb, but your script is doing Mon 26th Feb.
Even you example file does the same...
What am i missing?
- Greg_Deckler2 years ago
Community Champion
StuartSmith This depends on your logic. The way this is written, January 8th is working day +0, January 9th is working day +1 (from the Start Date). It seems you want to count the start date as the first working day. In that case, remove the +1 from the CALENDAR function so CALENDAR( [Start Date], [Start Date] + __Days)